NC-v4 SSc4:Rainwater management

Rainwater management

Dear Concern:-

we are working in a major renovation project so it is difficult to manage the runoff however we are reduce the runoff volume compared to     pre-development  by GI & LID 

 

we have following queries all about option - 2

 

1.The runoff after renovation can not increase compare with runoff before renovation, is it enough to get this credit (Landscape area increased so runoff in post development reduce by 3% compare with pre development)

2.It is already have maximum landscape, GI & LID techniques so it is difficult to manage the entire runoff

3.is it correct way to compare pre-development and post development for achieve this credit

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 01/02/2018 - 16:16

Option 2 requires you to manage the difference between the natural condition hydrology (pre) and the post development hydrology. FYI....pre-development means before the site was ever developed, not before you developed it. You need to run a continuous simulation model for this option (EPA SWMM, PCSWMM, etc)  