I've read practically all available resources, but I didn't find some details.
The fact is that we want to sertify our project in LEED. Now we haven't got completed project, but only ideas and intensions. How much time will we have after registration to make complete project? I can't understand what book we should buy to calculate and assess all items in rating system?
During review are requested some official documents or there are requested only completed forms from your site?
And another question: if I want to submit for Combined Design & Construction review, how much time do i have between application for project review and application for construction review?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Jean Marais
b.i.g. Bechtold DesignBuilder Expert832 thumbs up
March 11, 2010 - 7:53 am
http://www.gbci.org/DisplayPage.aspx?CMSPageID=156#Appeals_Policy
LEED for Existing Buildings, New Construction, Core & Shell, and Commercial Interiors
Application for Operations & Maintenance O&M or Combined Design & Construction (D&C) Review (Hereafter ‘Standard Review’)
Within two (2) years of substantial project completion (Combined D&C only, see LEED-EB: O&M rating system for O&M timeline requirements), the Owner shall submit, via LEED Online, a complete application for Standard Review. A complete application for Standard Review must include payment of the Standard Review fee and complete submittal documentation for 1) all prerequisites and enough credits to result in the minimum number of points required for certification.
Preliminary Standard Review
GBCI shall review and return comments for all credits and prerequisites included in the application for Standard Review. GBCI shall designate each credit and prerequisite reviewed as "anticipated," "pending,” or "denied." GBCI targets (but does not guarantee) delivery of the Preliminary Standard Review within twenty-five (25) business days of receipt of a completed application.
Response to Preliminary Standard Review
Within twenty-five (25) business days of GBCI’s delivery of the Preliminary Standard Review, the Owner may submit, via LEED-Online, a response to the preliminary Standard Review. Said response must include revised documentation for any prerequisite or credit submitted with the initial application for Standard Review.
Final Standard Review
GBCI shall review and return comments for all credits and prerequisites included in the response to the preliminary Standard Review. GBCI shall designate each credit and prerequisite reviewed as “awarded” or “denied.” GBCI targets (but does not guarantee) delivery of the Final Standard Review within fifteen (15) business days of receipt of a completed application. The Owner shall then accept or appeal the final Construction Review (see II. Appeals by Owner of CIRs and Credits/Prerequisites)