Hallo,
We've been asked by the reviewer to complete and submit the following table: https://www.usgbc.org/resources/performance-periods-table-v2009
What is the performance period in those credit where calculations have been made to demonstrate compliance or where only the signing of the policy is required? For instance:
-SSc5, SSc6, SSc7.1 and SSc7.2, WEp1, WEc3: Credits is demonstrated through calculations. What is the performance period we are supposed to state?
-MRc6. The waste stream audit must be PERFORMED within the 3 months of the shown performance period?
-IEQc2.1. The Green Cleaning policy must be SIGNED within the 3 months of the shown performance period?
-IEQp3. The Green Cleaning policy must be SIGNED within the 3 months of the shown performance period?
Has anyone wondered the same...?
Thanks!
Trista Brown
Project DirectorWSP USA
454 thumbs up
January 9, 2018 - 9:08 pm
Hi Gustavo, just a couple things to mention before I dive into your specific questions: overall you need to be sure that all performance periods (PP) end within the same 30 day window. Generally, teams will have a standard 3-month PP, with maybe a few credits ending within the broader 30-day window. And lastly, any given PP can last for up to 2 years total. I'll try to answer your specific questions but let me know if I missed anything:
- calculation credits: these can be set to your "standard" 3-month PP, so all you need to do is make sure you're following the above rules and that the PP listed in the table is for at least 3 months.
- waste audit: this needs to be conducted within the last 2 years, so you can set the PP to end at your normal PP end date, and just extend the credit PP back in time to capture when the audit was completed (up to 2 years back)
- green cleaning policy: the signature date doesn't really matter in my experience, but I'd recommend having it signed sometime before the PP start date for the green cleaning prerequisite/credits (that way, it "applies" to the whole performance period)
Hope that helps!
Gustavo De las Heras Izquierdo
LEED Expert184 thumbs up
January 10, 2018 - 11:40 am
Hi Trista, your comment is really useful! Thank you so much!
Gabriela Crespo
BECxP, CxA+BE, LEED AP BD+C, O+MRevitaliza Consultores
21 thumbs up
March 26, 2018 - 2:16 pm
Hi Guys! Following up on Gustavo's question, I was wondering about credits that do not require a performance period such as Water Efficient Landscaping or Building Commissiong-Investigation and Analysis or Increased Ventilation, can we write that the credit does not require a performance period?
Thank you!
Trista Brown
Project DirectorWSP USA
454 thumbs up
March 26, 2018 - 2:35 pm
I'd recommend plugging your standard performance period into credits that don't have specific PP requirements. But do remember to meet all the PP rules outlined above for credits that require one-time assessments or audits. So for example, if your energy audit was completed 7 months ago, you should ensure your PP end date aligns with your standard PP end date, but your PP start date extends back 7 months in order to include the audit. Make sense?
Gabriela Crespo
BECxP, CxA+BE, LEED AP BD+C, O+MRevitaliza Consultores
21 thumbs up
March 26, 2018 - 2:57 pm
Ok, got it!
Thanks Trista!
Divantha Ekanayake
March 3, 2020 - 12:09 am
Hi Folks,
Following up on Trista's comment, do we have to do the energy audit within the performance period?? As far as I understood it, only energy metering (12 months) is done withing the performance period in v4 standard. Anyways, we have to do the retrofitting based on the findings of the energy audit, before begin the measurements, so it takes some time anyways. Appreciate any input.
Trista Brown
Project DirectorWSP USA
454 thumbs up
March 3, 2020 - 7:24 pm
Hi Divantha, an energy audit performed within 2 years of your performance period end date can be used. If the audit was performed within 3-5 years of the PP end date, you can use it, but you must update it to reflect current operational practices, setpoints, energy costs, etc.