Forum discussion

NC-v4 EQc2:Low emitting materials

Option 2 : budget calculation method

Dear all, Under Option 2 how determine if furnitures are concerned ? Thank you !

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 10/29/2014 - 16:16

If furniture is part of the scope of work for the project, then include it in the credit evaluation. If furniture is a separate contract from the building construction, then you can exclude it.

Wed, 10/29/2014 - 17:15

Ok, it's very helpful. Thank you