Hi all, we received comments from reviewer that requesting the system computation should be separated for each system. Our development consists of few meeting rooms and open plan offices. The previous spreadsheet was combined since all the 4 AHUs is supplying fresh air to the same space volume. Anybody can help to explain?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Dylan Connelly
Mechanical EngineerIntegral Group
LEEDuser Expert
472 thumbs up
January 23, 2017 - 10:01 am
I would just give them what they want. Redo the spreadsheet w/ the 4 AHUs separate, estimate the space that each serve and cut some spaces if you have to. I don't necessarily agree with the response from GBCI, but easiest to just go with it. You could also send them a question through your LEED Admin if need additional clarity.