Has anyone had success pursuing credit for the BPDO EPD Option 2 (Multi Attribute Optimization)? The companies I have had success finding documentation for are as follows:
Owens Corning (Thermafiber), Interface (GlasBacRE), mulitple Sherwin Williams products (LCA Action Plans), and Milliken (WellBAC).
Does anyone have any great resources or tips for tracking these down? I need more companies/products that have this documentation.
Tommy Linstroth
CEOGreen Badger
LEEDuser Expert
90 thumbs up
February 26, 2021 - 8:40 am
Sarah, we put a blog post together on this - take a look, but this is what we've found.
https://getgreenbadger.com/2020/10/21/earning-mrc2-option-2-multi-attrib...
Allen Cornett
Sustainable ConsultantINSPEC Sustainability Group LLC
38 thumbs up
March 10, 2021 - 11:54 am
I have not seen any, but is anyone aware of a minimum square footage of paint that needs to be installed to be counted toward the criteria? I have a project considering accent walls using a few gallons of multiple products to get over the 10 product threshold. Thank you for your time.
Tommy Linstroth
CEOGreen Badger
LEEDuser Expert
90 thumbs up
March 10, 2021 - 12:00 pm
None that I've seen. Make the accent wall (or mechanical closet) shine!
Claudia Mezey
Assistant Consultant, Built EcologyWSP USA
6 thumbs up
March 10, 2021 - 12:01 pm
Hi Alan. That's right - the v4.1 Reference Guide/Addenda don't set a minimum quantity of a product. As long as it's permanently installed and within the relevant CSI divisions, you'll be able to count it.
Deborah Lucking
Director of SustainabilityFentress Architects
LEEDuser Expert
217 thumbs up
July 29, 2021 - 11:58 am
Tommy Linstroth,
did you take down the blog post you mentioned in your comment of Feb 26 2021?
Sarah Linke
AssociateGreenwood Consulting Group
3 thumbs up
July 29, 2021 - 12:16 pm
Here it is: https://getgreenbadger.com/earning-mrc2-option-2-multi-attribute-optimiz...
Tommy Linstroth
CEOGreen Badger
LEEDuser Expert
90 thumbs up
July 29, 2021 - 12:29 pm
Deborah,
We've updated it - we made a downloadable e-book with the latest and greatest that is available here.
There's also the web version as part of our Ultimate Guide to LEED Construction you can access here.
Erin Holdenried
Sustainable Design ManagerAECOM
31 thumbs up
February 17, 2022 - 11:03 pm
How does one establish a baseline to compare a product to? Can you use the EC3 tool, or does it require a building life cycle tool like Tally or OneClick?