I have a project where two forms of asbestos contamination has been identified. One on pipework and the other in the existing floor slab adhesive - SSc3 Brownfield development. The asbestos on pipework is to be removed. However, for the floor adhesive / slab the proposal is to apply a new compliant sealant locking in the existing adhesive. My question is, is this LEED complaint?
If an Asbestos Specialist confirms that this strategy remediates the building, does this comply with LEED?