We are pursuing in this credit the "Option 2: Providing onsite alternative fueling stations for 3% of total vehicle parking capacity is a bit more involved and potentially more expensive. The most readily accessible strategy here is providing plug outlets for electric cars"

The propierty is asking if we can achieve the credit with the installation of the electric chargers but in a progressive way. I mean, when we deliver all the documentation of the certification only the 50% of the electric charguers will be installed because the ocupation will incorpore the building in a stepped way. So they will be install the 100% once the full ocupation is on the building. The electric supply will be installed in all the correspondient parking places

Can we achieve the credit with the evidences of the first electric chargers installed and a letter with the commitment of the owner that will be install the rest during the ocupation phase? 

Thank you in advance