I look through the I Beam program (hope is did not miss out anything) and would like to ask few question here.
Q1 : do we need to do 100% survey (I Beam) for project we work on?
Q2 : When we need to start the I Beam Program? During or before performance period?
Q3: How many individual are encourage to join the I Beam Program at the day of the survey? for example , during the survey, 1 engineer will be good enough to do the program himself? If yes, then we can ask few engineer to difference floor to do the program at the same day as to save time.
Thanks
Jason Franken
Sustainability ProfessionalLEEDuser Expert
608 thumbs up
October 22, 2010 - 10:32 am
The I-BEAM survey materials try to address any possible scenario, so you can use some discretion when you conduct the walkthrough. The audit should be fully completed, but if there are questions or areas that do not apply to your project building, you may simply indicate "not applicable". You should identify a member of your project team as the IAQ Manager before the start of your performance period. Make it clear that their responsibilities for this role will not end when the LEED project is finished; periodic inspections should continue to take place after the initial audit is completed. The initial audit must take place during the performance period and any problems that can be addressed at no cost must be remedied immediately; for this reason, you should try to conduct the audit at least a few weeks prior to the end of your performance period so that you leave yourself enough time to correct these problems. It would be acceptable to have multiple engineers audit different floors of the building to save time; however, you must still identify a lead staff person as the IAQ Manager and make sure that they coordinate all of the efforts and collate all of the audit results into a single final report. It would also be a good idea to train each engineer in such a way so that the same methodology is used to conduct each of the audits; this will ensure that a standardized approach is used throughout the entire project building.
Simon Sue
SL+A INTERNATIONAL ASIA INC.411 thumbs up
October 24, 2010 - 10:59 pm
Thanks Jason, i do have another question as well.
We working on a commercial building with different tenant in each floor or sharing the same floor, the question is, do we need to do the survey at each tenant space or a random selection?
Besides that,
after identifying the problem , a schedule plan will be put in place (budget and, schedule to repair found issues) and i presume such report need to submit as a prove that we work on I BEAM, am i correct?
Jason Franken
Sustainability ProfessionalLEEDuser Expert
608 thumbs up
October 26, 2010 - 10:23 am
Well, the I-BEAM audit is designed to be an analysis of the entire project building, specifically the mechanical spaces, so you need to look at as much of the building as possible. It's not a survey so much as it is a building walkthrough. LEED allows you to exclude up to 10% of your gross floor area, so you can take that into consideration if you have one or more tenants who are not cooperative.
Yes, you will need to include a copy of the finished I-BEAM audit, as well as a narrative explaining how repairs or other corrective actions were handled.
Simon Sue
SL+A INTERNATIONAL ASIA INC.411 thumbs up
January 4, 2011 - 6:59 am
In regards to the I-BEAM audit, to our understanding, one baseline audit needs to be conducted within the performance period, and on-going audits are recommended to be performed "periodic." Is there a specific requirement or recommendation on how often an audit should be performed as part of the policy or plan language?
Jason Franken
Sustainability ProfessionalLEEDuser Expert
608 thumbs up
January 10, 2011 - 9:28 am
No specific requirement, so the project team is free to determine their own definition of periodic. I'd recommend, at minimum, that the audits are performed on an annual basis.
Simon Sue
SL+A INTERNATIONAL ASIA INC.411 thumbs up
January 10, 2011 - 7:50 pm
That sounds reasonable. Thank you for the input, Jason.