NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction

HVAC Equipment Installation prior to Roof

The contractor would like to install the HVAC equipment although the roof is not on the building yet. It would seem to me that as long as the contractor protects the equipment from moisture and contaminents this should still be in compliance with LEED requirements. They are not planing on using the equipment. Is there anything I am missing or should warn the contractor about?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 09/05/2013 - 17:12

As long as the equipment is well protected, I can't think of any reason why this strategy would not be ok.