ND-v2009 GIBc2:Building energy efficiency

(HERS) index score of at least 75

for a residential LEED ND project seeking LEED ND Plan certification only, the Homes that are required to achieve at least 75 HERS index. is providing a RESNET HERS model enough , or should the homes be confirmed on-site as well (conducting on-site confirmed rating)? what if the homes are not built yet?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Sat, 10/01/2016 - 20:52

Mugahid, modeling is enough, no onsite confirmation is necessary. By the way, your question was submitted under ND v2009, but you mention seeking ND Plan which is v4. Eliot