Our project had a combined review and the reviewer questioned hydro
RECs purchased by the owner as not being Green -e or equivalent.
The owner will purchase additional Green-e certified RECs from the same
company in addition to the former. Therefore will enter into a new contract
beginning now, before we submit the final response. This should satisfy the requirements for the credit correct? ( the contract start date is not an issue? but rather the duration and amount? correct?).... Thanks Suzy
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5914 thumbs up
September 4, 2012 - 4:29 pm
You can purchase additional or replacement RECs in between the review phases and the start date will not be an issue.