My project is a government building, which is being built in an exclusively governmental area. only government buildings are constructed in this area. is a government administrative center.
there are no residential buildings around. still, I can get the credit?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Trey Akers
August 11, 2014 - 3:43 pm
Hi Patricia,
Your project would be eligible to pursue this credit via Option 1 Development Density, which does not require a certain residential density. The Option 2 pathway, Community Connectivity, requires at least one neighborhood with at least 10 dwelling units per acre to be within a one-half mile radius of the project's main entrance.