Jason,
You can request an extention through GBCI for some reasonable timeframe, say 2 weeks (10 business days) extra. I believe this is usually acceptable but of course, your request could be denied, it is up to their discression.
The avenue for making this request has changed somewhat, so I'd suggest calling GBCI to get detailed information on the latest procedures.
Good luck!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Simon Sue
SL+A INTERNATIONAL ASIA INC.411 thumbs up
December 4, 2011 - 11:12 pm
Hi Emily,
thanks for the advice. do you experience in extending the timeframe? We thinking to email the reviewer team, because of the time zone different.
Susan Walter
HDRLEEDuser Expert
1296 thumbs up
December 5, 2011 - 9:15 am
Email would also work but a phone call is quickest. We've had extensions up to 25 days.
Simon Sue
SL+A INTERNATIONAL ASIA INC.411 thumbs up
December 5, 2011 - 7:44 pm
Hi Susan,
Doesn't GBCI need a written note or email to keep as record?
be possible to share with me, what is the reason you told GBCI for the extension of 25days?
Manny Iglesia
LEED BD+C O+MCarde Ten Architects
121 thumbs up
December 5, 2011 - 8:05 pm
Normally, you set the no. of days you need. Say, you are waiting for a mail to arrive any day now or the LEED Admin is on-leave for a month or Design Consultant replaced with a new one. Tell the true story and the Reviewer will ascertain whether your request is valid. Or if you are just vying time because the Client hasn't decided yet on buying Green Power or Solar Panel, you might as well use the Appeal for a fee.
Simon Sue
SL+A INTERNATIONAL ASIA INC.411 thumbs up
December 5, 2011 - 8:13 pm
Hey Romano, thanks.
we wondering about the written record if were to call gbci team. somehow thanks for the advise.
Manny Iglesia
LEED BD+C O+MCarde Ten Architects
121 thumbs up
December 5, 2011 - 8:17 pm
The Rep. that will take your call will change the dates on the spot and will send you (LEED Project Admin & all LEED Project Manager) an email confirming your request.
Simon Sue
SL+A INTERNATIONAL ASIA INC.411 thumbs up
December 5, 2011 - 8:18 pm
that's great, appreciate your note.
Susan Walter
HDRLEEDuser Expert
1296 thumbs up
December 6, 2011 - 8:15 am
Jason, Agree with Romano. We needed the extension due to other project deadlines and they sent the confirming email.