Forum discussion

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy

Expansion project FLUSH OUT

We have a project that is an expansion to an existing facility. It is NOT an addition. Though the majority of the existing facility was unrenovated, with the exception of one ventilation system that was tied into the renovation portion. The existing portion was isolated and documented in IEQc3.1. Do we have to flush out all of the existing unrenovated portion, since the GBCI reviewer is requesting we also document this? We only flushed out the expansion (new AHUs) and the areas that are communicated with the expansion. Thank You

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.