Do I have to account for the water use of existing fixtures to remain on a major renovation (football stadium) under LEED NC, if they are within the LEED boundary, but the spaces/structures they are located in are not being touched in any manner as part of the scope of work? If yes, do I use the actual fixture flow for each existing fixture?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Crina Bosch
Project CoordinatorKarpinski Engineering
October 24, 2013 - 3:47 pm
Any luck with this? We are facing the same issue in a building in a campus setting.
ERIC TAYLOR
2 thumbs up
October 24, 2013 - 4:30 pm
Not yet, we have also sent this question and some additional credit questions into GBCI directly to see how each credit will be affected by the existing spaces/systems.