Our project is on a university campus that has an existing biofuel station for fleet vehicles. The biofuel station services the entire campus and is not located with our LEED boundary for this project. Could we receive credit for Option 2, if the existing station can supply fuel for 3% of the total vehicle capacity of the site? Would there be any additional documentation to upload besides the required information on the number of stations, alternative fuel type, manufacturer, model number, and fueling capacity per station?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Helen Kessler
PresidentHJKessler Associates
51 thumbs up
April 2, 2015 - 2:03 pm
When you say site, do you mean the entire campus or do you mean just your one project. The biofuel stations would likely need to serve 3% of the total vehicle capacity of the campus.