We're submitting a project where we have 42% of electricity and 58% of gas consumption. And out of 42% of electricity consumption, 9.2% is generated on-site.
Do we have to purchase 35% over a 2-year period for the 100% of energy consumption (including both electricity and gas)? Or do we have to buy 35% over a 2-year period for the 42% of electricity consumption minus the energy generated on-site?
Thanks in advance for your answers.
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5916 thumbs up
June 28, 2021 - 10:25 am
The latter