Hi,

I'm trying to figure out what the earliest date is that we could deliver a LEED certification to our client, assuming no appeals, etc. I'm working out a timeline where I'm starting with the latest occurring credit and working backwards to understand our To Dos - the latest credit seems to be Fundamental Cx (we're not pursuing Enhanced). Does this seem right? Does the submittal for Fundamental Cx require that the systems start-up has already happened (since we are submitting a report), i.e. means that we certainly wouldn't be able to achieve certification before TCO (temporary cert of occ)? Besides collecting all the Materials credit information through end of construction, are there other credits that would hang us up at the end of the process? 

Thanks,
Hannah