Why does no one ask for paper work to verify that material is shipped by rail or water? There are so many manufactures that fill out the submission documents and lie about how it got to the job Site.
This puts honest manufacturers at a disadvantage for both cost and lead time. Not only is there added transportation costs, material may take up to 3 times as long to be delivered by rail as it does by truck.