General Question: If a project is submitting their LEED information in the two part Design and Construction approach, do all the of credits which are noted as being "Design" credits have to actually be submitted during that Design submission or can some of those "Design" credits be deferred until the final Construction Submission?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
K Nakamura
4 thumbs up
July 1, 2014 - 2:05 pm
You can defer Design credits to the Construction submittal. Furthermore, if you apply for Innovation in Design Credits in the Design Submittal that get rejected in the final design ruling, you are able to apply for a different Innovation Credit in the Construction Submittal.