Hi Folks,
We received the final decisiona on a very complicated industrial building we are pursuing certification for and EAp2 and IEQp1 were denied. We are appealing, but process has been going on for over 3 months now...it requires project updates and extra info from vendors that we are having a hard time to get on board. Is there a maximum deadline we have to submit documentation by? Any particular/special procedure we should take in this type of case? This building is part of a campus of 4 buildings and the 3 other buildings sucessfully achieved LEED certification. All 4 were built under the same contract and pursued LEED under the same process.
Thanks!
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
January 13, 2015 - 9:57 am
Generally you have 25 working days to respond. You can ask for extensions. If you do not formally ask for an extension you basically get one anyway as they do not finalize the review until you respond. I am not aware of any formal cut off date but know that some projects take more than a year to respond.