Do the projects under core and shell have to providde dedicated exhasut systems for tenant print or copy rooms? The guide seems to say that they don't need to but they ask to include this in the lease agreement? What should be included?
Thanks"!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Dylan Connelly
Mechanical EngineerIntegral Group
LEEDuser Expert
472 thumbs up
July 21, 2013 - 12:43 pm
M K
There should be previsions made to allow for exhaust of those space to be installed by a tenant during a TI build out. Typically we leave capped ducts in a convient places off of the base buildings restroom exhaust system. The exhaust fans should be capable of handling the extra exhaust flow from those spaces in the future.
In addition, put it in the lease agreement as you stated.