My project has 30% of carparking reserved for electric vehicles. The plugs used comply with an IEC standard but not the one specfied in the credit requirements. Furthermore the demand response programe is not an option, nor is the network capabilities.
However, the intent of the credit is met by the reservation of 30% which is 15x what is required. Would this be accepted?
Thanks