Is there a minimum building occupancy % for the 12 month performance period? I am working on an office tower that has slowly increased it occupancy over the last year. I am wondering when we can legitimately start the monitoring period.
Thanks!
Forum discussion
EBOM-2009 EAc1: Optimize Energy Performance
Is there a minimum building occupancy % for the 12 month performance period? I am working on an office tower that has slowly increased it occupancy over the last year. I am wondering when we can legitimately start the monitoring period.
Thanks!
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Our building includes a large laboratory space. Can our project benchmark under the Labs21 program?
How long is an Energy Star label valid to use with a streamlined approach for Case 1?
When is it possible to exclude up to 10% of the building from EAp2?
How do I account for computers with multiple monitors on Portfolio Manager?
Jason Franken
Sustainability ProfessionalLEEDuser Expert
608 thumbs up
June 19, 2012 - 11:47 am
Yes, the Minimum Program Requirements (MPRs) mandate at least 50% occupancy over the previous 12 months (55% for hotels) under the EBOM Rating System. You can review a summary of the MPRs here: http://www.leeduser.com/strategy/minimum-program-requirements