Hi, 

I have encountered an issue with the baseline model for Data Center , based on LEED Comments we are using system 8 and for climate zone 5a the economizer shut off limit is 70F, the data center that i am working on is in Chicago where 7100 hrs in the year are below 70 F, which means that baseline system is using free cooling when our proposed system dont have an economizer, what can I do in that case? Like we are not able to even get minimum savings as baseline is getting free cooling.