Requirements
Create and implement an erosion and sedimentation control plan for all construction activities associated with the project. The plan must conform to the erosion and sedimentation requirements of the 2003 EPA Construction General Permit OR local standards and codes, whichever is more stringent. [India ACP: E&S Plan]. The plan must describe the measures implemented to accomplish the following objectives:
- To prevent loss of soil during construction by stormwater runoff and/or wind erosion, including protecting topsoil by stockpiling for reuse.
- To prevent sedimentation of storm sewers or receiving streams.
- To prevent pollution of the air with dust and particulate matter.
Credit substitution available
You may use the LEED v4 version of this credit on v2009 projects. For more information check out this article.Alternative Compliance Paths (ACPs)
India ACP: EPA Construction General Permit Equivalent
Projects in India may use the National Building Code of India 2005 (NBC 2005) Part 10, Section 1, Chapters 4 & 5 along with Section 3 of the EPA Construction General Permit[view:embed_resource=page_1=10039154]SITES-LEED Equivalency
This LEED credit (or a component of this credit) has been established as equivalent to a SITES v2 credit or component. For more information on using the equivalency as a substitution in your LEED or SITES project, see this article and guidance document.What does it cost?
Cost estimates for this credit
On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.
Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.
This information is also available in a full PDF download in The Cost of LEED v4 report.
Learn more about The Cost of LEED v4 »Frequently asked questions
Am I exempt from this prerequisite if I have a zero-lot-line building? What if the site work is minimal due to the scope? What about a renovation? What if the excavation and foundation work is minimal due to the construction materials I am using?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
What are BMPs for steep slopes?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
I have a technical question about a specific control measure and whether LEED requires it. What guidance is available?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
Is there a preferred method for documentation?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
What suffices as far as a date-stamped photo?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
Can I still earn the prerequisite if the project started considering LEED after work began?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
Checklists
Step by step to LEED certification
LEEDuser’s checklists walk you through the key action steps you need to earn a credit, including how to avoid common pitfalls and save money.
Documentation toolkit
The motherlode of cheat sheets
LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.
Get the inside scoop
Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
Create and implement an erosion and sedimentation control plan for all construction activities associated with the project. The plan must conform to the erosion and sedimentation requirements of the 2003 EPA Construction General Permit OR local standards and codes, whichever is more stringent. [India ACP: E&S Plan]. The plan must describe the measures implemented to accomplish the following objectives:
- To prevent loss of soil during construction by stormwater runoff and/or wind erosion, including protecting topsoil by stockpiling for reuse.
- To prevent sedimentation of storm sewers or receiving streams.
- To prevent pollution of the air with dust and particulate matter.
Credit substitution available
You may use the LEED v4 version of this credit on v2009 projects. For more information check out this article.Alternative Compliance Paths (ACPs)
India ACP: EPA Construction General Permit Equivalent
Projects in India may use the National Building Code of India 2005 (NBC 2005) Part 10, Section 1, Chapters 4 & 5 along with Section 3 of the EPA Construction General Permit[view:embed_resource=page_1=10039154]SITES-LEED Equivalency
This LEED credit (or a component of this credit) has been established as equivalent to a SITES v2 credit or component. For more information on using the equivalency as a substitution in your LEED or SITES project, see this article and guidance document.XX%
Upgrade to LEEDuser Premium to see how many projects achieved this credit. Try it free »
Got the gist of SSp1 but not sure how to actually achieve it? LEEDuser gives step-by-step help. Premium members get:
- Checklists covering all the key action steps you'll need to earn the credit.
- Hot tips to give you shortcuts and avoid pitfalls.
- Cost tips to assess what a credit will actually cost, and how to make it affordable.
- Ideas for going beyond LEED with best practices.
- All checklists organized by project phase.
- On-the-fly suggestions of useful items from the Documentation Toolkit and Credit Language.
In the end, LEED is all about documentation. LEEDuser’s Documentation Toolkit, for premium members only, saves you time and helps you avoid mistakes with:
- Calculators to help assess credit compliance.
- Tracking spreadsheets for materials purchases.
- Spreadsheets and forms to give to subs and other team members.
- Guidance documents on arcane LEED issues.
- Sample templates to help guide your narratives and LEED Online submissions.
- Examples of actual submissions from certified LEED projects.
Am I exempt from this prerequisite if I have a zero-lot-line building? What if the site work is minimal due to the scope? What about a renovation? What if the excavation and foundation work is minimal due to the construction materials I am using?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
What are BMPs for steep slopes?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
I have a technical question about a specific control measure and whether LEED requires it. What guidance is available?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
Is there a preferred method for documentation?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
What suffices as far as a date-stamped photo?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
Can I still earn the prerequisite if the project started considering LEED after work began?The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |