Frank advice from LEED experts

LEED is changing all the time, and every project is unique. Even seasoned professionals can miss a critical detail and lose a credit or even a prerequisite at the last minute. Our expert advice guides our LEEDuser Premium members and saves you valuable time.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Create and implement an erosion and sedimentation control plan for all construction activities associated with the project. The plan must conform to the erosion and sedimentation requirements of the 2003 EPA Construction General Permit OR local standards and codes, whichever is more stringent. [India ACP: E&S Plan]. The plan must describe the measures implemented to accomplish the following objectives:

  • To prevent loss of soil during construction by stormwater runoff and/or wind erosion, including protecting topsoil by stockpiling for reuse.
  • To prevent sedimentation of storm sewers or receiving streams.
  • To prevent pollution of the air with dust and particulate matter.
The EPA’s construction general permit outlines the provisions necessary to comply with Phase I and Phase II of the National Pollutant Discharge Elimination System (NPDES) program. While the permit only applies to construction sites greater than 1 acre, the requirements are applied to all projects for the purposes of this prerequisite. Information on the EPA construction general permit is available at http://cfpub.epa.gov/ npdes/stormwater/cgp.cfm.
Credit substitution available
You may use the LEED v4 version of this credit on v2009 projects. For more information check out this article.

Alternative Compliance Paths (ACPs)

India ACP: EPA Construction General Permit Equivalent
Projects in India may use the National Building Code of India 2005 (NBC 2005) Part 10, Section 1, Chapters 4 & 5 along with Section 3 of the EPA Construction General Permit[view:embed_resource=page_1=10039154]
SITES-LEED Equivalency
This LEED credit (or a component of this credit) has been established as equivalent to a SITES v2 credit or component. For more information on using the equivalency as a substitution in your LEED or SITES project, see this article and guidance document.
See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

Get the inside scoop

Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Create and implement an erosion and sedimentation control plan for all construction activities associated with the project. The plan must conform to the erosion and sedimentation requirements of the 2003 EPA Construction General Permit OR local standards and codes, whichever is more stringent. [India ACP: E&S Plan]. The plan must describe the measures implemented to accomplish the following objectives:

  • To prevent loss of soil during construction by stormwater runoff and/or wind erosion, including protecting topsoil by stockpiling for reuse.
  • To prevent sedimentation of storm sewers or receiving streams.
  • To prevent pollution of the air with dust and particulate matter.
The EPA’s construction general permit outlines the provisions necessary to comply with Phase I and Phase II of the National Pollutant Discharge Elimination System (NPDES) program. While the permit only applies to construction sites greater than 1 acre, the requirements are applied to all projects for the purposes of this prerequisite. Information on the EPA construction general permit is available at http://cfpub.epa.gov/ npdes/stormwater/cgp.cfm.
Credit substitution available
You may use the LEED v4 version of this credit on v2009 projects. For more information check out this article.

Alternative Compliance Paths (ACPs)

India ACP: EPA Construction General Permit Equivalent
Projects in India may use the National Building Code of India 2005 (NBC 2005) Part 10, Section 1, Chapters 4 & 5 along with Section 3 of the EPA Construction General Permit[view:embed_resource=page_1=10039154]
SITES-LEED Equivalency
This LEED credit (or a component of this credit) has been established as equivalent to a SITES v2 credit or component. For more information on using the equivalency as a substitution in your LEED or SITES project, see this article and guidance document.
See all LEEDuser forum discussions about this credit » Subscribe to new discussions about Retail-NC-v2009 SSp1