Energy-Related Pilot Credits
GridOptimal Building ACP

LEED CREDIT

Pilot-Credits EApc152: GridOptimal Building ACP 3 points

LEEDuser’s viewpoint

Explore this LEED credit

Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

For LEED v4 BD+C projects, this pilot ACP is available as an alternative to LEED v4 EA credit Demand Response. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.

For LEED v4.1 BD+C projects, this pilot ACP is available as an alternative to LEED v4.1 EA credit Grid Harmonization. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.


Option 1: Calculate and Report GridOptimal Performance (1 point)
Using the energy simulation developed to document compliance with the EA Minimum Energy Performance prerequisite or Optimize Energy Performance credit, and following the technical guidance herein, calculate GridOptimal metrics for the baseline and proposed building cases. Submit the completed LEED GridOptimal calculator.

GridOptimal metrics to be calculated include:
  1. Grid Peak Contribution
  2. Grid Carbon Alignment
  3. Site Renewable Utilization Efficiency
  4. Short-Term Demand Flexibility
  5. Long-Term Demand Flexibility
  6. Dispatchable Demand Flexibility
Calculate and report scores for all six GridOptimal Metrics for both the baseline and design building. For each GridOptimal metric for which the Design Score is lower than the Baseline Score, produce a narrative that describes technologies or strategies that would have improved the Design Score that were deemed unacceptable to implement by the project team.

Option 2: Across-The-Board Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1
AND
Demonstrate Minimum Score Improvement as detailed in Table 1 for at least three GridOptimal Metrics (2 points) or all six GridOptimal Metrics (2 points plus 1 Innovation Point).

Table 1.
GridOptimal Metric Minimum Score Improvement
Grid Peak Contribution 10
Grid Carbon Alignment 5
Site Renewable Utilization Efficiency 10
Short-Term Demand Flexibility 15
Long-Term Demand Flexibility 10
Dispatchable Demand Flexibility 5

Option 3: Focused Area Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1
Demonstrate Moderate Score Improvement (2 points) or Exemplary Score Improvement (2 points plus 1 Innovation Point) as detailed in Table 2 for at least one of the six GridOptimal Metrics.

Table 2.
GridOptimal Metric Moderate Score Improvement Exemplary Score Improvement
Grid Peak Contribution 20 30
Grid Carbon Alignment 10 20
Site Renewable Utilization Efficiency 20 30
Short-Term Demand Flexibility 25 35
Long-Term Demand Flexibility 15 20
Dispatchable Demand Flexibility 10 15

Submittals

General
Register for the pilot credit Feedback Survey
Documentation/Compliance
  • GridOptimal Calculator
Changes
  • 2/9/21 - Original Publication
  • 4/12/22 - updates to thresholds, calculator compatibility functionality, sample calculator provided
See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

For LEED v4 BD+C projects, this pilot ACP is available as an alternative to LEED v4 EA credit Demand Response. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.

For LEED v4.1 BD+C projects, this pilot ACP is available as an alternative to LEED v4.1 EA credit Grid Harmonization. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.


Option 1: Calculate and Report GridOptimal Performance (1 point)
Using the energy simulation developed to document compliance with the EA Minimum Energy Performance prerequisite or Optimize Energy Performance credit, and following the technical guidance herein, calculate GridOptimal metrics for the baseline and proposed building cases. Submit the completed LEED GridOptimal calculator.

GridOptimal metrics to be calculated include:
  1. Grid Peak Contribution
  2. Grid Carbon Alignment
  3. Site Renewable Utilization Efficiency
  4. Short-Term Demand Flexibility
  5. Long-Term Demand Flexibility
  6. Dispatchable Demand Flexibility
Calculate and report scores for all six GridOptimal Metrics for both the baseline and design building. For each GridOptimal metric for which the Design Score is lower than the Baseline Score, produce a narrative that describes technologies or strategies that would have improved the Design Score that were deemed unacceptable to implement by the project team.

Option 2: Across-The-Board Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1
AND
Demonstrate Minimum Score Improvement as detailed in Table 1 for at least three GridOptimal Metrics (2 points) or all six GridOptimal Metrics (2 points plus 1 Innovation Point).

Table 1.
GridOptimal Metric Minimum Score Improvement
Grid Peak Contribution 10
Grid Carbon Alignment 5
Site Renewable Utilization Efficiency 10
Short-Term Demand Flexibility 15
Long-Term Demand Flexibility 10
Dispatchable Demand Flexibility 5

Option 3: Focused Area Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1
Demonstrate Moderate Score Improvement (2 points) or Exemplary Score Improvement (2 points plus 1 Innovation Point) as detailed in Table 2 for at least one of the six GridOptimal Metrics.

Table 2.
GridOptimal Metric Moderate Score Improvement Exemplary Score Improvement
Grid Peak Contribution 20 30
Grid Carbon Alignment 10 20
Site Renewable Utilization Efficiency 20 30
Short-Term Demand Flexibility 25 35
Long-Term Demand Flexibility 15 20
Dispatchable Demand Flexibility 10 15

Submittals

General
Register for the pilot credit Feedback Survey
Documentation/Compliance
  • GridOptimal Calculator
Changes
  • 2/9/21 - Original Publication
  • 4/12/22 - updates to thresholds, calculator compatibility functionality, sample calculator provided

In the end, LEED is all about documentation. LEEDuser’s Documentation Toolkit, for premium members only, saves you time and helps you avoid mistakes with:

  • Calculators to help assess credit compliance.
  • Tracking spreadsheets for materials purchases.
  • Spreadsheets and forms to give to subs and other team members.
  • Guidance documents on arcane LEED issues.
  • Sample templates to help guide your narratives and LEED Online submissions.
  • Examples of actual submissions from certified LEED projects.
See all LEEDuser forum discussions about this credit » Subscribe to new discussions about Pilot-Credits EApc152