LEEDuser’s viewpoint
Explore this LEED credit
Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.
Credit language
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
For LEED v4 BD+C projects, this pilot ACP is available as an alternative to LEED v4 EA credit Demand Response. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.For LEED v4.1 BD+C projects, this pilot ACP is available as an alternative to LEED v4.1 EA credit Grid Harmonization. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.
Option 1: Calculate and Report GridOptimal Performance (1 point)
Using the energy simulation developed to document compliance with the EA Minimum Energy Performance prerequisite or Optimize Energy Performance credit, and following the technical guidance herein, calculate GridOptimal metrics for the baseline and proposed building cases. Submit the completed LEED GridOptimal calculator.GridOptimal metrics to be calculated include:
- Grid Peak Contribution
- Grid Carbon Alignment
- Site Renewable Utilization Efficiency
- Short-Term Demand Flexibility
- Long-Term Demand Flexibility
- Dispatchable Demand Flexibility
Option 2: Across-The-Board Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1AND
Demonstrate Minimum Score Improvement as detailed in Table 1 for at least three GridOptimal Metrics (2 points) or all six GridOptimal Metrics (2 points plus 1 Innovation Point).
Table 1.
GridOptimal Metric | Minimum Score Improvement |
---|---|
Grid Peak Contribution | 10 |
Grid Carbon Alignment | 5 |
Site Renewable Utilization Efficiency | 10 |
Short-Term Demand Flexibility | 15 |
Long-Term Demand Flexibility | 10 |
Dispatchable Demand Flexibility | 5 |
Option 3: Focused Area Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1Demonstrate Moderate Score Improvement (2 points) or Exemplary Score Improvement (2 points plus 1 Innovation Point) as detailed in Table 2 for at least one of the six GridOptimal Metrics.
Table 2.
GridOptimal Metric | Moderate Score Improvement | Exemplary Score Improvement |
---|---|---|
Grid Peak Contribution | 20 | 30 |
Grid Carbon Alignment | 10 | 20 |
Site Renewable Utilization Efficiency | 20 | 30 |
Short-Term Demand Flexibility | 25 | 35 |
Long-Term Demand Flexibility | 15 | 20 |
Dispatchable Demand Flexibility | 10 | 15 |
Submittals
General
Register for the pilot credit- Participate in the optional LEEDuser pilot credit forum
- Complete the feedback survey:
Documentation/Compliance
- GridOptimal Calculator
Changes
- 2/9/21 - Original Publication
- 4/12/22 - updates to thresholds, calculator compatibility functionality, sample calculator provided
What does it cost?
Cost estimates for this credit
On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.
Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.
This information is also available in a full PDF download in The Cost of LEED v4 report.
Learn more about The Cost of LEED v4 »Frequently asked questions
See all forum discussions about this credit »Documentation toolkit
The motherlode of cheat sheets
LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
For LEED v4 BD+C projects, this pilot ACP is available as an alternative to LEED v4 EA credit Demand Response. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.For LEED v4.1 BD+C projects, this pilot ACP is available as an alternative to LEED v4.1 EA credit Grid Harmonization. Project teams may earn up to 2 points plus one exemplary performance point depending on the Option pursued.
Option 1: Calculate and Report GridOptimal Performance (1 point)
Using the energy simulation developed to document compliance with the EA Minimum Energy Performance prerequisite or Optimize Energy Performance credit, and following the technical guidance herein, calculate GridOptimal metrics for the baseline and proposed building cases. Submit the completed LEED GridOptimal calculator.GridOptimal metrics to be calculated include:
- Grid Peak Contribution
- Grid Carbon Alignment
- Site Renewable Utilization Efficiency
- Short-Term Demand Flexibility
- Long-Term Demand Flexibility
- Dispatchable Demand Flexibility
Option 2: Across-The-Board Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1AND
Demonstrate Minimum Score Improvement as detailed in Table 1 for at least three GridOptimal Metrics (2 points) or all six GridOptimal Metrics (2 points plus 1 Innovation Point).
Table 1.
GridOptimal Metric | Minimum Score Improvement |
---|---|
Grid Peak Contribution | 10 |
Grid Carbon Alignment | 5 |
Site Renewable Utilization Efficiency | 10 |
Short-Term Demand Flexibility | 15 |
Long-Term Demand Flexibility | 10 |
Dispatchable Demand Flexibility | 5 |
Option 3: Focused Area Improvement (2 points + 1 ID point)
Comply with the requirements of Option 1Demonstrate Moderate Score Improvement (2 points) or Exemplary Score Improvement (2 points plus 1 Innovation Point) as detailed in Table 2 for at least one of the six GridOptimal Metrics.
Table 2.
GridOptimal Metric | Moderate Score Improvement | Exemplary Score Improvement |
---|---|---|
Grid Peak Contribution | 20 | 30 |
Grid Carbon Alignment | 10 | 20 |
Site Renewable Utilization Efficiency | 20 | 30 |
Short-Term Demand Flexibility | 25 | 35 |
Long-Term Demand Flexibility | 15 | 20 |
Dispatchable Demand Flexibility | 10 | 15 |
Submittals
General
Register for the pilot credit- Participate in the optional LEEDuser pilot credit forum
- Complete the feedback survey:
Documentation/Compliance
- GridOptimal Calculator
Changes
- 2/9/21 - Original Publication
- 4/12/22 - updates to thresholds, calculator compatibility functionality, sample calculator provided
In the end, LEED is all about documentation. LEEDuser’s Documentation Toolkit, for premium members only, saves you time and helps you avoid mistakes with:
- Calculators to help assess credit compliance.
- Tracking spreadsheets for materials purchases.
- Spreadsheets and forms to give to subs and other team members.
- Guidance documents on arcane LEED issues.
- Sample templates to help guide your narratives and LEED Online submissions.
- Examples of actual submissions from certified LEED projects.