Requirements

FOR ALL PROJECTS
All options apply to existing natural or constructed slopes. Portions of project sites with slopes up to 20 feet (6 meters) in elevation, measured from toe (a distinct break between a 40% slope and lesser slopes) to top, that are more than 30 feet (9 meters) in any direction from another slope greater than 15% are exempt from the requirements, although more restrictive local regulations may apply.
OPTION 1. No Disturbance of Slopes Over 15%
Locate on a site that has no existing slopes greater than 15%, or avoid disturbing portions of the site that have existing slopes greater than 15%.

OR

OPTION 2. Previously Developed Sites with Slopes Over 15%
On portions of previously developed sites with existing slopes greater than 15%, restore the slope area with native plants or noninvasive adapted plants according to Table 1.
Table 1. Required restoration area of slope

Slope

Restoration

> 40%

100%

26% to 40%

60%

15% to 25%

40%

In addition, develop covenants, conditions, and restrictions (CC&R); development agreements; or other binding documents that will protect the specified steep slope areas in perpetuity. Comply with the requirements of Option 3 on any slope over 15% that has not been previously developed.

OR

OPTION 3. Sites Other than Previously Developed Sites with Slopes Over 15%
On sites that are not previously developed sites, protect existing slopes over 15% as follows:
  1. Do not disturb slopes greater than 40% and do not disturb portions of the project site within 50 feet (15 meters) horizontally of the top of the slope and 75 feet (23 meters) horizontally from the toe of the slope.
  2. Limit development to no more than 40% of slopes between 25% and 40% and to no more than 60% of slopes between 15% and 25%.
  3. Locate development such that the percentage of the development footprint that is on existing slopes less than 15% is greater than the percentage of buildable land that has existing slopes less than 15%.
  4. Develop CC&R, development agreements, or other binding documents that will protect steep slopes in perpetuity.
See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Addenda

2/2/2011Updated: 2/14/2015
Rating System Correction
Description of change:
Replace the first line of text with "On sites that are not previously developed sites, protect existing slopes over 15% as follows:"
Campus Applicable
No
Internationally Applicable:
No
2/2/2011Updated: 2/14/2015
Reference Guide Correction
Description of change:
Replace the text in item A of the legend with "
Campus Applicable
No
Internationally Applicable:
No
2/2/2011Updated: 2/14/2015
Reference Guide Correction
Description of change:
Replace the text in item A of the legend with "
Campus Applicable
No
Internationally Applicable:
No
2/2/2011Updated: 2/14/2015
Reference Guide Correction
Description of change:
Replace the first line of text with "On sites that are not previously developed sites, protect existing slopes over 15% as follows:"
Campus Applicable
No
Internationally Applicable:
No
2/2/2011Updated: 2/14/2015
Rating System Correction
Description of change:
Replace "OPTION 3. Undeveloped Sites with Slopes Over 15%" with "Sites Other than Previously Developed Sites with Slopes Over 15%"
Campus Applicable
No
Internationally Applicable:
No
2/2/2011Updated: 2/14/2015
Reference Guide Correction
Description of change:
In the fourth row, insert a "
Campus Applicable
No
Internationally Applicable:
No
2/2/2011Updated: 2/14/2015
Reference Guide Correction
Description of change:
Replace "OPTION 3. Undeveloped Sites with Slopes Over 15%" with "Sites Other than Previously Developed Sites with Slopes Over 15%"
Campus Applicable
No
Internationally Applicable:
No
2/2/2011Updated: 2/14/2015
Rating System Correction
Description of change:
In the fourth row, insert a "
Campus Applicable
No
Internationally Applicable:
No
See all forum discussions about this credit »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

FOR ALL PROJECTS
All options apply to existing natural or constructed slopes. Portions of project sites with slopes up to 20 feet (6 meters) in elevation, measured from toe (a distinct break between a 40% slope and lesser slopes) to top, that are more than 30 feet (9 meters) in any direction from another slope greater than 15% are exempt from the requirements, although more restrictive local regulations may apply.
OPTION 1. No Disturbance of Slopes Over 15%
Locate on a site that has no existing slopes greater than 15%, or avoid disturbing portions of the site that have existing slopes greater than 15%.

OR

OPTION 2. Previously Developed Sites with Slopes Over 15%
On portions of previously developed sites with existing slopes greater than 15%, restore the slope area with native plants or noninvasive adapted plants according to Table 1.
Table 1. Required restoration area of slope

Slope

Restoration

> 40%

100%

26% to 40%

60%

15% to 25%

40%

In addition, develop covenants, conditions, and restrictions (CC&R); development agreements; or other binding documents that will protect the specified steep slope areas in perpetuity. Comply with the requirements of Option 3 on any slope over 15% that has not been previously developed.

OR

OPTION 3. Sites Other than Previously Developed Sites with Slopes Over 15%
On sites that are not previously developed sites, protect existing slopes over 15% as follows:
  1. Do not disturb slopes greater than 40% and do not disturb portions of the project site within 50 feet (15 meters) horizontally of the top of the slope and 75 feet (23 meters) horizontally from the toe of the slope.
  2. Limit development to no more than 40% of slopes between 25% and 40% and to no more than 60% of slopes between 15% and 25%.
  3. Locate development such that the percentage of the development footprint that is on existing slopes less than 15% is greater than the percentage of buildable land that has existing slopes less than 15%.
  4. Develop CC&R, development agreements, or other binding documents that will protect steep slopes in perpetuity.
See all LEEDuser forum discussions about this credit » Unsubscribe from discussions about ND-v2009 SLLc6