Building reuse - maintain existing walls, floors and roof

LEED CREDIT

Healthcare-v2009 MRc1.1: Building reuse - maintain existing walls, floors and roof 1-3 points

LEEDuser’s viewpoint

Frank advice from LEED experts

LEED is changing all the time, and every project is unique. Even seasoned professionals can miss a critical detail and lose a credit or even a prerequisite at the last minute. Our expert advice guides our LEEDuser Premium members and saves you valuable time.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Intent

To extend the life cycle of existing building stock, conserve resources, retain cultural resources, reduce waste and reduce environmental impacts of new buildings as they relate to materials manufacturing and transport.

Requirements

Maintain the existing building structure (including structural floor and roof decking) and envelope (the exterior skin and framing, excluding window assemblies and non-structural roofing material). The minimum percentage building reuse for each point threshold is as follows:

Hazardous materials that are remediated as a part of the project must be excluded from the calculation of the percentage maintained. Calculate the total area of existing exterior envelope and existing building structure to ensure that the credit goals have been met. Building materials demolished to create courtyards to increase daylighting may be counted as retained in calculations for this credit, provided that the new courtyards meet the requirements of IEQ Credit 8.2: Daylight and Views. If the project includes an addition that is more than 2 times the square footage of the existing building, this credit is not applicable.

Use only areas (square footage) to calculate the quantity of preserved materials. The area to be used in the denominator is the sum of all new and reused floor or roof area and the exterior envelope, including the ground floor, to account for slabs-on-grade and footings or the exterior wall area. The area to be used in the numerator is the sum of reused floor, roof or wall area.

See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

Get the inside scoop

Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Intent

To extend the life cycle of existing building stock, conserve resources, retain cultural resources, reduce waste and reduce environmental impacts of new buildings as they relate to materials manufacturing and transport.

Requirements

Maintain the existing building structure (including structural floor and roof decking) and envelope (the exterior skin and framing, excluding window assemblies and non-structural roofing material). The minimum percentage building reuse for each point threshold is as follows:

Hazardous materials that are remediated as a part of the project must be excluded from the calculation of the percentage maintained. Calculate the total area of existing exterior envelope and existing building structure to ensure that the credit goals have been met. Building materials demolished to create courtyards to increase daylighting may be counted as retained in calculations for this credit, provided that the new courtyards meet the requirements of IEQ Credit 8.2: Daylight and Views. If the project includes an addition that is more than 2 times the square footage of the existing building, this credit is not applicable.

Use only areas (square footage) to calculate the quantity of preserved materials. The area to be used in the denominator is the sum of all new and reused floor or roof area and the exterior envelope, including the ground floor, to account for slabs-on-grade and footings or the exterior wall area. The area to be used in the numerator is the sum of reused floor, roof or wall area.

See all LEEDuser forum discussions about this credit » Subscribe to new discussions about Healthcare-v2009 MRc1.1