Healthcare-v2009 IDp1: Integrated project planning and design Required

LEEDuser’s viewpoint

Explore this LEED credit

Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Use cross discipline design and decision-making, beginning in the programming and pre-design phase. At a minimum, ensure the following process:

  • ƒƒOwner’s Project Requirements Document. Prepare an Owner’s Project Requirements document for the project. Prepare a Health Mission Statement and incorporate it in the Owner’s Project Requirements. The health mission statement should address “triple bottom line” values—economic, environmental, and social—and include goals to safeguard the health of building occupants, the local community, and the global environment while creating a high performance healing environment for the building’s patients, caregivers, and staff.
  • ƒƒPreliminary Rating Goals. As early as practicable and preferably before Schematic Design, conduct a Preliminary LEED meeting including a minimum of four key project team members, in addition to the Owner or Owner’s representative. As part of the meeting, create a LEED® action plan that, at a minimum, includes the following:
    • The targeted LEED certification level (Certified, Silver, Gold, or Platinum);
    • The LEED credits that have been selected to meet the targeted certification level; and
    • The primary responsible party selected to meet the LEED requirements for each prerequisite and selected credit.
  • ƒIntegrated Project Team. Assemble and involve a minimum of four of the following project team members from the list below, in addition to the Owner or Owner’s representative, and as many as feasible.
    • Owner’s Capital Budget Manager
    • Architect or Building Designer
    • Mechanical Engineer
    • Electrical Engineer
    • Structural Engineer
    • Energy Modeler
    • Equipment Planner
    • Acoustical Consultant
    • Telecommunications Designer
    • Controls Designer
    • Building Science or Performance Testing Agents
    • Green Building or Sustainable Design Consultant
    • Facility Green Teams
    • Physician and Nursing Teams
    • Facility Managers
    • Environmental Services Staff
    • Functional and Space Programmers
    • Interior Designer
    • Lighting Consultant/Designer
    • Commissioning Agent
    • Community Representatives
    • Civil Engineering
    • Landscape Architecture
    • Habitat Restoration
    • Land Planning
    • Construction Management or General Contractor
    • Life Cycle Cost Analysis; Construction Cost Estimating
    • Other disciplines appropriate to the specific project type
  • Design Charrette. As early as practicable and preferably before schematic design, conduct at least one full-day integrated design charrette with the Integrated Project Team as defined above. The goal of the charrette shall be to optimize the integration of green strategies across all aspects of the building design, drawing on the expertise of all participants.
See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Use cross discipline design and decision-making, beginning in the programming and pre-design phase. At a minimum, ensure the following process:

  • ƒƒOwner’s Project Requirements Document. Prepare an Owner’s Project Requirements document for the project. Prepare a Health Mission Statement and incorporate it in the Owner’s Project Requirements. The health mission statement should address “triple bottom line” values—economic, environmental, and social—and include goals to safeguard the health of building occupants, the local community, and the global environment while creating a high performance healing environment for the building’s patients, caregivers, and staff.
  • ƒƒPreliminary Rating Goals. As early as practicable and preferably before Schematic Design, conduct a Preliminary LEED meeting including a minimum of four key project team members, in addition to the Owner or Owner’s representative. As part of the meeting, create a LEED® action plan that, at a minimum, includes the following:
    • The targeted LEED certification level (Certified, Silver, Gold, or Platinum);
    • The LEED credits that have been selected to meet the targeted certification level; and
    • The primary responsible party selected to meet the LEED requirements for each prerequisite and selected credit.
  • ƒIntegrated Project Team. Assemble and involve a minimum of four of the following project team members from the list below, in addition to the Owner or Owner’s representative, and as many as feasible.
    • Owner’s Capital Budget Manager
    • Architect or Building Designer
    • Mechanical Engineer
    • Electrical Engineer
    • Structural Engineer
    • Energy Modeler
    • Equipment Planner
    • Acoustical Consultant
    • Telecommunications Designer
    • Controls Designer
    • Building Science or Performance Testing Agents
    • Green Building or Sustainable Design Consultant
    • Facility Green Teams
    • Physician and Nursing Teams
    • Facility Managers
    • Environmental Services Staff
    • Functional and Space Programmers
    • Interior Designer
    • Lighting Consultant/Designer
    • Commissioning Agent
    • Community Representatives
    • Civil Engineering
    • Landscape Architecture
    • Habitat Restoration
    • Land Planning
    • Construction Management or General Contractor
    • Life Cycle Cost Analysis; Construction Cost Estimating
    • Other disciplines appropriate to the specific project type
  • Design Charrette. As early as practicable and preferably before schematic design, conduct at least one full-day integrated design charrette with the Integrated Project Team as defined above. The goal of the charrette shall be to optimize the integration of green strategies across all aspects of the building design, drawing on the expertise of all participants.
See all LEEDuser forum discussions about this credit » Subscribe to new discussions about Healthcare-v2009 IDp1