Log in
LEED v2009
Healthcare
Energy and Atmosphere

Enhanced refrigerant management

LEED CREDIT

Healthcare-v2009 EAc4: Enhanced Refrigerant Management 1 point

See all forum discussions about this credit »

LEEDuser expert

Paul Swierc

CEM, CPMP, BECxP, CxA+BE, EIT, LEED GA

Senior Commissioning Agent

LEEDuser’s viewpoint

Frank advice from LEED experts

LEED is changing all the time, and every project is unique. Even seasoned professionals can miss a critical detail and lose a credit or even a prerequisite at the last minute. Our expert advice guides our LEEDuser Premium members and saves you valuable time.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Option 1
Do not use refrigerants.

OR

Option 2
Select refrigerants and heating, ventilating, air conditioning and refrigeration (HVAC&R) equipment that minimize or eliminate the emission of compounds that contribute to ozone depletion and climate change. The base building HVAC&R equipment must comply with the following formula, which sets a maximum threshold for the combined contributions to ozone depletion and global warming potential: See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Addenda

10/1/2012Updated: 2/14/2015
Global ACP
Description of change:
Add a metric unit column to the first table as follows: Metric units LCGWP + LCODP x 105 = 13 Calculation definitions for LCGWP + LCODP x 105 = 13 (Metric units) LCODP = [ODPr x (Lr x Life +Mr) x Rc]/Life LCGWP = [GWPr x (Lr x Life +Mr) x Rc]/Life LCODP: Lifecycle Ozone Depletion Potential (kg CFC 11/(kW/year)) LCGWP: Lifecycle Direct Global Warming Potential (kg CO2/(kW/year)) ODPr: Ozone Depletion Potential of Refrigerant (0 to 0.2 kg CFC 11/kg r) GWPr: Global Warming Potential of Refrigerant (0 to 12,000 kg CO2/kg r) Lr: Refrigerant Leakage Rate (0.5% to 2.0%; default of 2% unless otherwise demonstrated) Mr: End-of-life Refrigerant Loss (2% to 10%; default of 10% unless otherwise demonstrated) Rc: Refrigerant Charge (0.065 to 0.65 kg of refrigerant per kW of ARI rated or Eurovent Certified cooling capacity) Life: Equipment Life (default based on equipment type, unless otherwise demonstrated)
Campus Applicable
No
Internationally Applicable:
Yes
10/1/2012Updated: 2/14/2015
Global ACP
Description of change:
Metric units = 13 S ( LCGWP + LCODP x 105 ) x Qunit --------------------------- Qtotal Add the following metric units to the second table in Option 2:
Campus Applicable
No
Internationally Applicable:
Yes
5/9/2011Updated: 2/14/2015
Reference Guide Correction
Description of change:
Update equation on bottom of page to read:? (LCGWP + LCODP x 105) x Qunit ? 100 Qtotal
Campus Applicable
No
Internationally Applicable:
No
10/1/2012Updated: 2/14/2015
Global ACP
Description of change:
Add the following metric units to the third table: Calculation definitions for [ S (LCGWP + LCODP x 105) x Qunit ] / Qtotal = 13 (Metric units) Qunit = Eurovent Certified cooling capacity of an individual HVAC or refrigeration unit (kW) Qtotal = Total Eurovent Certified cooling capacity of all HVAC or refrigeration (kW)
Campus Applicable
No
Internationally Applicable:
Yes
5/9/2011Updated: 2/14/2015
Reference Guide Correction
Description of change:
Replace the two bulleted items with the following:?Qunit = Gross ARI rated cooling capacity of an individual HVAC or refrigeration unit (tons)?Qtotal = Total Gross ARI rated cooling capacity of all HVAC or refrigeration
Campus Applicable
No
Internationally Applicable:
No
5/9/2011Updated: 2/14/2015
Rating System Correction
Description of change:
Update equation on bottom of page to read:? (LCGWP + LCODP x 105) x Qunit ? 100 Qtotal
Campus Applicable
No
Internationally Applicable:
No
7/1/2016
LEED Interpretation
Inquiry:

Our project is connected to a district energy system which provides both heating and cooling for the building; no additional building-level cooling systems are installed. The district system draws heavily on deep lake cooling with a complement of refrigerant-based cooling. We also have walk-in refrigerators on the premises. We are not permitted to count the deep lake cooling with a refrigerant factor of zero, so because the walk-in refrigerators use refrigerants with a high impact (according to the LEED calculation), we exceed the impact limit of 100 for the credit even though the project?s cooling capacity is largely provided by refrigerant-free sources.
We propose a calculation methodology that demonstrates a design case reduction of the total refrigerant impact as compared to the baseline case:
• The baseline case is calculated by factoring the total cooling capacity of the building?s baseline case and a refrigerant impact of 100 per ton. The demand (during the simulated year) is 1496 kW for the baseline case and 1704 (483,9 tons) installed capacity, as per the EAp2 form and the EA Section 1.4 Tables respectively.
o total design case cooling capacity = 483.9 tons
o total refrigerant impact = 483.9 x 100 = 48390

• The design case factors the labeled capacity on the district energy system?s heat exchanger (district cooling exchanger) and the walk-in refrigerator equipment, and their respective refrigerants.
o total design case cooling capacity = 393.7 tons
o total refrigerant impact = 393.7 x 86 = 33798

• Total reduction in cooling demand = 393.7 / 483.9 = 81.36 (18.64% reduction)
• Total reduction in refrigerant impact = 33798 / 48390 = 69.85 (30.15% reduction)

The calculation confirms that the refrigerant impact reduction is in excess of that associated with the reduced cooling capacity. We would like this to be an ACP.

Ruling:

The applicant proposes an alternate approach to the enhanced refrigerant impact credit which allows credit for the portion of cooling that is provided by systems that contain no refrigerants.

It is acceptable for the applicant to document that the refrigerant impact for the project (including downstream and upstream systems) is less than a refrigerant impact allowance calculated based on the Baseline cooling capacity* from the EAp2: Minimum Energy Performance Baseline energy model. However, the allowance calculated based on the cooling capacity shall be limited to 75 per ton (versus 100 per ton allowed using the compliance path defined in the Rating System Language for Proposed equipment).

To calculate the Baseline case allowance, multiply the total Baseline cooling capacity from the EAp2: Minimum Energy Performance model by a refrigerant impact of 75 per ton (in this case 483.9 x 75 = 36,292).

To calculate the Proposed case refrigerant impact, complete the EAc4: Refrigerant Impact form for the proposed systems (including upstream and on-site equipment). [Note: for upstream equipment, enter the capacity of the upstream equipment by multiplying the equipment capacity by the proportion of building loads to total district energy cooling loads. For example, if the building loads represent 10% of the district energy cooling loads, multiply the capacity of each piece of upstream equipment by 10%].

If the total refrigerant impact for the proposed design (including upstream systems) is less than the Baseline refrigerant impact allowance identified above, the project shall be deemed to comply with this alternative compliance path.

If using this path, please ensure that energy simulation output files showing both the Baseline cooling and refrigeration capacities AND the Baseline cooling and refrigeration peak operating capacities are uploaded either in EAp2: Minimum Energy Performance or in this credit.

* For the purposes of this Alternative Refrigerant Impact calculation, all uncooled spaces must be excluded from the total Baseline cooling capacity reported unless the documentation demonstrates how passive cooling has been achieved for these spaces.

Campus Applicable
No
Internationally Applicable:
Yes
See all forum discussions about this credit »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

LEEDuser expert

Paul Swierc

CEM, CPMP, BECxP, CxA+BE, EIT, LEED GA

Senior Commissioning Agent

Get the inside scoop

Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Option 1
Do not use refrigerants.

OR

Option 2
Select refrigerants and heating, ventilating, air conditioning and refrigeration (HVAC&R) equipment that minimize or eliminate the emission of compounds that contribute to ozone depletion and climate change. The base building HVAC&R equipment must comply with the following formula, which sets a maximum threshold for the combined contributions to ozone depletion and global warming potential:

LEEDuser expert

Paul Swierc

CEM, CPMP, BECxP, CxA+BE, EIT, LEED GA

Senior Commissioning Agent

See all LEEDuser forum discussions about this credit » Unsubscribe from discussions about Healthcare-v2009 EAc4