LEEDuser’s viewpoint
Frank advice from LEED experts
LEED is changing all the time, and every project is unique. Even seasoned professionals can miss a critical detail and lose a credit or even a prerequisite at the last minute. Our expert advice guides our LEEDuser Premium members and saves you valuable time.
Credit language

© Copyright U.S. Green Building Council, Inc. All rights reserved.
Intent
To begin the commissioning process early in the design process and execute additional activities after systems performance verification is completed.
Requirements
Implement, or have a contract in place to implement, the following additional commissioning process activities in addition to the requirements of EA Prerequisite 1: Fundamental Commissioning of Building Energy Systems and in accordance with the LEED Green Building Design and Construction Reference Guide, 2009 Edition Healthcare Supplement:
Option 1 (1 point)
- Prior to the start of the construction documents phase, designate an independent commissioning authority (CxA) to lead, review and oversee the completion of all commissioning process activities. The CxA shall, at a minimum, perform Tasks 2, 3, and 6. Other team members may perform Tasks 4 and 5.
- The CxA must have documented commissioning authority experience in at least two building projects.
- The individual serving as the CxA:
- Must be independent of the work of design and construction.
- Must not be an employee of the design firm, though he or she may be contracted through them.
- Must not be an employee of, or contracted through, a contractor or construction manager holding construction contracts.
- May be a qualified employee or consultant of the owner.
Option 2 (2 points)
Achieve OPTION 1 AND Commission the building’s thermal envelope systems in accordance with the requirements of Option 1. Commissioning of the building envelope shall be in accordance with ASHRAE Guideline 0-2005, the Commissioning Process, and National Institute of Building Sciences (NIBS) Guideline 3-2006, Exterior Enclosure Technical Requirements for the Commissioning Process. The building thermal envelope entails all exterior wall assemblies separating a building’s conditioned spaces from outdoor ambient conditions, including: roof assemblies, vapor barriers, diffusion retarders, air barrier systems, rain-screen layers, flashings, cladding and siding, windows, curtain-wall assemblies, doors, thermal bridges , and utility penetrations, such as piping, electrical conduit, duct-banks and other entry-points made for routing HVAC system components. For major renovations, substantial performance upgrades must be installed on at least 25% of the exterior envelope surface area. In support of the process requirements in Option 1, the following sequence of steps shall be taken to ensure an effective building thermal envelope commissioning process:- Convene meeting to review with the entire green building project team the goals and objectives of the process and coordinate/assign the related tasks.
- Conduct building thermal envelope design review.
- Develop thermal envelope commissioning work plan and schedule.
- Develop coordinated documentation plan.
- Ascertain functional performance test and inspection procedures (i.e. determine reference standards).
- Review thermal envelope components and assemblies mock-ups where relevant.
- Conduct scheduled field quality assurance inspections per work plan; document inspections.
- Inspect corrections of defects encountered during inspections.
- Prepare final report.
What does it cost?
Cost estimates for this credit
On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.
Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.
This information is also available in a full PDF download in The Cost of LEED v4 report.
Learn more about The Cost of LEED v4 »Frequently asked questions
Who can perform enhanced commissioning services? The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
If my project uses a District Energy System (DES) is enhanced commissioning required for the DES? The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
Documentation toolkit
The motherlode of cheat sheets
LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.
Get the inside scoop
Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.

© Copyright U.S. Green Building Council, Inc. All rights reserved.
Intent
To begin the commissioning process early in the design process and execute additional activities after systems performance verification is completed.
Requirements
Implement, or have a contract in place to implement, the following additional commissioning process activities in addition to the requirements of EA Prerequisite 1: Fundamental Commissioning of Building Energy Systems and in accordance with the LEED Green Building Design and Construction Reference Guide, 2009 Edition Healthcare Supplement:
Option 1 (1 point)
- Prior to the start of the construction documents phase, designate an independent commissioning authority (CxA) to lead, review and oversee the completion of all commissioning process activities. The CxA shall, at a minimum, perform Tasks 2, 3, and 6. Other team members may perform Tasks 4 and 5.
- The CxA must have documented commissioning authority experience in at least two building projects.
- The individual serving as the CxA:
- Must be independent of the work of design and construction.
- Must not be an employee of the design firm, though he or she may be contracted through them.
- Must not be an employee of, or contracted through, a contractor or construction manager holding construction contracts.
- May be a qualified employee or consultant of the owner.
Option 2 (2 points)
Achieve OPTION 1 AND Commission the building’s thermal envelope systems in accordance with the requirements of Option 1. Commissioning of the building envelope shall be in accordance with ASHRAE Guideline 0-2005, the Commissioning Process, and National Institute of Building Sciences (NIBS) Guideline 3-2006, Exterior Enclosure Technical Requirements for the Commissioning Process. The building thermal envelope entails all exterior wall assemblies separating a building’s conditioned spaces from outdoor ambient conditions, including: roof assemblies, vapor barriers, diffusion retarders, air barrier systems, rain-screen layers, flashings, cladding and siding, windows, curtain-wall assemblies, doors, thermal bridges , and utility penetrations, such as piping, electrical conduit, duct-banks and other entry-points made for routing HVAC system components. For major renovations, substantial performance upgrades must be installed on at least 25% of the exterior envelope surface area. In support of the process requirements in Option 1, the following sequence of steps shall be taken to ensure an effective building thermal envelope commissioning process:- Convene meeting to review with the entire green building project team the goals and objectives of the process and coordinate/assign the related tasks.
- Conduct building thermal envelope design review.
- Develop thermal envelope commissioning work plan and schedule.
- Develop coordinated documentation plan.
- Ascertain functional performance test and inspection procedures (i.e. determine reference standards).
- Review thermal envelope components and assemblies mock-ups where relevant.
- Conduct scheduled field quality assurance inspections per work plan; document inspections.
- Inspect corrections of defects encountered during inspections.
- Prepare final report.
Who can perform enhanced commissioning services? The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |
If my project uses a District Energy System (DES) is enhanced commissioning required for the DES? The answer to this question is available to LEEDuser premium members. Start a free trial » (If you're already a premium member, log in here.) |