Log in

Cost Tip

Schedule the application of paints and coatings so that offgassing does not contaminate other absorptive materials. This is required if projects are attempting EQc3.1: Construction Indoor Air Quality Plan—During Construction. For example, do not store or

Schedule the application of paints and coatings so that off-gassing does not contaminate other absorptive materials. This is required if projects are attempting IEQc3.1: Construction Indoor Air Quality Plan—During Construction. For example, do not store or install acoustic ceiling tile before flooring and wall paints are put down, because ceiling tiles will absorb the off-gassing of paint and contaminate the air over a longer time period.