The M&V provider writes the M&V plan, but if possible, involve the facility’s operational staff. The plan must provide the following (see a sample M&V plan in the Documentation Toolkit):standard IPMVP language and terminologywhich option or me

The M&V provider writes the M&V plan, but if possible, involve the facility’s operational staff. The plan must provide the following (see a sample M&V plan in the Documentation Toolkit):

  • standard IPMVP language and terminology
  • which option or method from the document will be used
  • who will conduct the M&V program
  • assumptions about significant variables or unknowns
  • an accurate baseline using techniques appropriate to your project
  • the method of ensuring an accurate energy-savings determination 
  • a post-installation inspection plan
  • criteria for equipment metering, calibration, and measurement period
  • the level of accuracy to be achieved by all major components
  • quality assurance measures
  • the contents of reports to be prepared, along with a schedule. 