If existing equipment uses CFCs and will be retained, prepare a phase-out plan for conversion to an appropriate CFC-free refrigerant or a plan for equipment replacement.
- Conversion: Your conversion plan should include specifications for the current system, with current and proposed refrigerant types and a firm timetable for refrigerant replacement. The plan should be developed by your mechanical engineer in collaboration with the tenant or owner, printed on official letterhead, and signed by the appropriate facilities or operations manager.
- Replacement: Your replacement plan should include specifications for the new system and a firm timetable for system replacement, as well as designation of your proposed system and preferred, system-specific refrigerant.