IAQ testing should be worked into the construction schedule as it will occur close to project close-out, generally when the construction schedule is most critical. Testing will take a least one day, but could take longer depending on the number of tests required. If any tests are failed, flush-out and retesting are required and will have significant scheduling impacts. This could require several additional days.