The following work must be completed prior to flush-out or testing to ensure that the air quality isn't compromised afterward.All interior finishes must be installed.All punch-list items must be complete. All cleaning must be finalized.Final testing

The following work must be completed prior to flush-out or testing to ensure that the air quality isn't compromised afterward.

  • All interior finishes must be installed.
  • All punch-list items must be complete. 
  • All cleaning must be finalized.
  • Final testing and balancing of HVAC systems must be complete. Other commissioning tasks can occur during flush-out or testing only if they do not introduce any additional contaminants into the building.
  • Temporary filters and duct coverings used as part of the construction IAQ management plan must be removed.
  • Filters must be replaced with new filtration media, unless the system is configured to filter only outside air. If your project is pursuing IEQc5: Indoor Chemical and Pollutant Source Control, these filters must be MERV 13 or higher.
  • For BD&C projects, it is optional to install furniture and furnishings prior to testing or flush-out. For ID&C projects, movable furnishings must be installed prior to testing or flush-out.