Even after the 50% construction documents review, CxA will not be required to meet again. Even then, it is useful to let the CxA know of the design progress. Include them on the weekly meeting-minutes mailing lists. Design changes may affect the commissio

Even after the 50% construction documents review, CxA will not be required to meet again. Even then, it is useful to let the CxA know of the design progress. Include them on the weekly meeting-minutes mailing lists. Design changes may affect the commissioning plan, to be commissioned equipment list, and probably the commissioning scope.