Determine whether IPMVP Option B or Option D is most appropriate for your project design:
- Option B is based on engineering calculations using metered data and is generally more appropriate for buildings with non-interactive loads only.
- Option D uses calibrated, whole-building energy simulations for both the baseline and design case and is generally more appropriate for larger, more complex building projects using an energy model.