Ongoing Commissioning Overlap with New Building CommissioningEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Doug Pierce, AIA on Aug 10, 2010, 7:16 pm
Has anyone purused this credit for a project previously receiving the Enhanced Commissioning Credit for LEED NC Certification? And if so, do you know if the performance period for the EB On-going... Last reply: Sonrisa Lucero, Jul 12, 2011, 3:41 pm |
|
Frequency of InspectionsEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Maria Unruh on Nov 8, 2010, 5:06 pm
In looking to achieve this credit, I am planning on writing a... Last reply: Pierce Holstrom, Nov 8, 2010, 7:44 pm |
|
New Chiller Installation & Performance PeriodEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Dana Dinolfo on Jan 21, 2011, 12:34 pm
Hello: We are beginning an... Last reply: Maria Unruh, Jan 21, 2011, 12:53 pm |
|
Scope of comissioningEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Iris Amdur on Apr 27, 2011, 3:25 pm
Hello- We're working on a building that is not owner occupied and the tenant has 48 additional pieces of equipment that are not a part of the... Last reply: Jacob Arlein, Mar 2, 2012, 3:51 pm |
|
Comments from a LEED reviewEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Raphael Sperry on Jun 3, 2011, 4:50 pm
We just received comments on a review of this credit I am trying to understand. For this project, we actually had an approved MV plan from LEED NC credit EAc5. The plan is very detailed and... Last reply: Jacob Arlein, Feb 21, 2012, 5:36 pm |
|
PNNL Re-Tuning MethodologyEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Mike Barker on Jul 13, 2012, 1:41 am
How about considering the PNNL Re-Tuning Methodology as a pilot credit ? It is a complete process - techniques and skills - and includes training of staff. See... Last reply: Mike Barker, Jul 22, 2012, 3:13 am |
|
EAc2.1 workEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Elizabeth Crenshaw Hammitt on Nov 2, 2012, 9:48 am
From reading these comments, it seems like any work done EAc2.1 MAY NOT count toward this credit. Activities that were done for EAc2.1 would have to be repeated, making EAc2.1 a baseline case...... Last reply: Eric Anderson, Feb 8, 2013, 5:35 pm |
|
Doing both the Level II assessment and credit EA2.3 "ongoing Cx"EBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Tom Kennedy on May 1, 2013, 6:46 pm
Our team sees benefit to doing both, and making a deliberate effort to place energy-items into either the "audit" or "... Last reply: Arpit Chhapola, May 15, 2017, 12:27 am |
|
Ongoing Cx RequirementsEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Colleen Collins on May 6, 2013, 2:33 pm
I have a question regarding EA2.3 As I understand it, it appears that the ongoing... Last reply: Hannah Bronfman, Nov 7, 2013, 4:16 pm |
|
EAc2.3- Ongoing Cx formsEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Alexis Voeltner on Jan 20, 2015, 3:06 pm
Hi Hannah, do you have an example of what the on-going... |