Forum

Forum » EBOM-2009 EAc1
Topic

The Naming of Options, and Knowing Which Applies to You

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Jenny Carney on Jan 5, 2010, 3:08 pm

I just received an email with this question: "How do you know which calculator to use when trying to figure out the National Average. Your helpful hints indicate to use either calculator C or B....

Energy Star Portfolio Manager

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Reynaldo Castro on May 10, 2010, 6:42 pm

I have a question in regards to the Energy Star Portfolio Manager. We are currently purchasing 30% offsite...

Last reply: Jenny Carney, May 12, 2010, 10:35 am

Energy Star Portfolio Manager- Professional Engineer Sign Off?

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Miriam Gee on May 19, 2010, 7:50 pm

Does LEED require a P.E. to sign the Energy Star Portfolio Manager report? Or is this only required if they are applying for the Energy Star Rating plaque (score of 75 or higher).

Thank...

Last reply: Srimannarayana NCVK, Mar 30, 2012, 2:26 pm

Uploading Portfolio Manager

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by David Sheridan on Jun 2, 2010, 1:13 pm

How does one upload a PM file to LEED Online (this is 'old' LEED Online)

Do I need to make a screen shot and then paste that on a Word file?

Last reply: Jason Franken, Jun 7, 2010, 9:59 am

Energy Star and Fire Stations

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Kath Williams on Jun 16, 2010, 11:32 am

How do Fire stations qualify for Energy Star ratings? Do we need a year’s of supporting data to show the building energy consumption to be 123 kBtu/Sqft or less to certify under LEED-EB: O&M...

Last reply: Jenny Carney, Jul 12, 2010, 3:35 pm

EBOM 2009: Performance period possible before registration?

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Kelly Knauss on Jul 13, 2010, 12:59 pm

It's not clear to me if energy consumption data collected for EA credit 1 (energy performance) needs to be from the period after registering an...

Last reply: Tristan Roberts, Jul 19, 2010, 4:53 pm

Is a single meter reading for a campus acceptable?

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Yong Lee Low on Jul 29, 2010, 11:46 pm

If the project is a 3 building campus,and I split the space types into 6-7 categories but my meter reading is just from a single feeding point i.e. just 1 meter for the entire campus ,will that...

My project is a resort where

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Yong Lee Low on Jul 30, 2010, 12:32 am

My project is a resort where it is divided into 3 buildings: main hotel building with rooms and f&b facilities,The other two buildings are supporting the recreation facilities like gym,spa...

Last reply: Jenny Carney, Aug 11, 2010, 3:28 pm

Energy Star and Energy & Water Data Release Form

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Pablo Fortunato Suarez on Aug 9, 2010, 4:35 am

1) if a project obtains a score of 96 in Energy Star, this counts as 18 points?
2) where do we upload the accomplished Energy and Water Data Release Form?

Last reply: Pablo Fortunato Suarez, Aug 24, 2010, 10:59 pm

Energy Star Partner

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Simon Sue on Aug 12, 2010, 5:38 am

Hi.

We have a project here back in Taiwan and we need to achieved some credit for EAC1. I get to know that US EPA Energy Star has international program with other countries as to promote...

Last reply: Simon Sue, Aug 16, 2010, 10:04 pm
Post a question