Extra Point = Building Performance Partnership

CS-2009 EAc5.1: Measurement and verification - base building
posted by Alison Y Rivenburgh on May 17, 2010, 4:57 pm

From the USGBC website:
"LEED 2009 for New Construction, LEED 2009 for Core & Shell, or LEED 2009 for Schools projects that participate in BPP Data Collection Phase 1 and signing a...

Last reply: Marcus Sheffer, Dec 1, 2011, 1:40 pm

M&V Reporting Period

CS-2009 EAc5.1: Measurement and verification - base building
posted by Robyn Williams Heeks on Jul 7, 2010, 11:12 am

For the MPRs for a Core & Shell project, the five year data reporting period begins when occupancy achieves 50% of its "Typical Physical Occupancy". Is the start point the same for M&V...

Last reply: Gordon Shymko, Jul 14, 2010, 12:17 pm

A question on a related subject

CS-2009 EAc5.1: Measurement and verification - base building
posted by Jose Salinas on Jul 29, 2010, 3:50 pm

Tristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11477 thumbs up August 16, 2010- 12:36 pm We were just discussing this very question under the LEED-EBOM EAc1 forum. I will refer you to that conversation. Log in or register to post comments ...

Last reply: Tristan Roberts, Aug 16, 2010, 12:36 pm

M&V Plan for base building

CS-2009 EAc5.1: Measurement and verification - base building
posted by Joel Kerschen on Aug 2, 2010, 11:01 am

I am currently working on an M&V plan for the...

Last reply: Gordon Shymko, Aug 2, 2010, 4:18 pm

M&V Plan- Questions

CS-2009 EAc5.1: Measurement and verification - base building
posted by Maya Karkour on Aug 25, 2010, 6:06 am

Dear all,

I am attempting LEED 2009 CS, EA Cr 5.1 & Cr 5.2.

My project is 4 multi-storey commercial buildings, whereby a different tenant occupies each floor of a building....

Last reply: Christopher Schaffner, Aug 25, 2010, 9:36 am

Occupancy Calcs

CS-2009 EAc5.1: Measurement and verification - base building
posted by Robyn Williams Heeks on Dec 6, 2010, 1:03 pm

I understand that occupancy calculations are to be consistent between all credits. For PIf3 Space Usage calculations, we used the default occupancies given by LEED in Appendix 2009. We...

Last reply: Gordon Shymko, Dec 29, 2010, 6:21 pm

Calibration to actual energy use??

CS-2009 EAc5.1: Measurement and verification - base building
posted by javier bolanos zeledon on Dec 13, 2010, 5:20 am

Hi, I don't understand why the reference guide is asking to calibrate the as-built simulation model to the actual energy use. In a new construction there is no actual energy use yet, unless you...

Last reply: Marcus Sheffer, Jun 26, 2012, 8:42 pm

ASHREA Simulation vs. actual building operations

CS-2009 EAc5.1: Measurement and verification - base building
posted by Susann Geithner on Dec 15, 2010, 6:10 pm

When we enter the calculated consumptions from EA P2 into the EA C5.1 LEED Online form, can I than use other values, which are based on actual building operation and performance?
We deal...

Last reply: Gordon Shymko, Apr 24, 2011, 4:09 pm

Core & Shell M&V

CS-2009 EAc5.1: Measurement and verification - base building
posted by Randy Cook on Mar 2, 2012, 2:50 pm

Hello, I have read thru the previous posts and responses, and hope this is not a redundant question. I am working on a C&S major renovation. We are going to follow Option B from...

Last reply: Marcus Sheffer, Mar 2, 2012, 5:13 pm

M&V period for LEED 2009 C&S projects for EAc5.1 + EAc5.2

CS-2009 EAc5.1: Measurement and verification - base building
posted by Philip Herriges on Jul 17, 2012, 11:16 am

The LEED reference guide is very particular in the language that they use to describe the intent and stragegies for EAc5.1 and 5.2 for C&S as being distinct from NC & Schools.

For...

Last reply: Marcus Sheffer, Jul 17, 2012, 12:26 pm