Forum
| Topic | Recent |
|---|---|
Determining Total Materials BudgetCI-2009 MRc3.1: Materials Reuseposted by Adolfo Silva on Jun 24, 2010, 3:22 pm
We are working on a CI project which has a significant amount of reused construction materials and furniture. Should we include the replacement cost or the actual cost of construction... Last reply: David Posada, Jun 24, 2010, 5:44 pm |
|
Re-used Food Service/Commercial Kitchen EquipmentCI-2009 MRc3.1: Materials Reuseposted by Suzanne Painter-Supplee, LEED AP+ID&C on Oct 27, 2010, 8:09 pm
I have had conflicting information regarding re-used commercial kitchen equipment, whose energy and water are measured as 'process.' Some say yes, others no. There are mechanical, electrical and... Last reply: Jack Boti, Jun 12, 2024, 10:14 am |
|
Reclaimed White Oak for Materials ReuseCI-2009 MRc3.1: Materials Reuseposted by Alan Bernstein on Nov 29, 2010, 7:32 pm
I am using a reclaimed white oak... Last reply: Tristan Roberts, Nov 29, 2010, 9:38 pm |
|
Airport jetway re-useCI-2009 MRc3.1: Materials Reuseposted by Raphael Sperry on Feb 23, 2011, 6:41 pm
We have an unusual case in an airport project I am working on. It is LEED-CI as we are refurbishing a passenger concourse and some of the back-of-house spaces that go with it. There are 11... Last reply: Eric Shamp, Feb 27, 2011, 11:25 pm |
|
Manufacturer's Stockpile MaterialCI-2009 MRc3.1: Materials Reuseposted by Gary Keyfauver on Apr 10, 2011, 4:52 pm
I work for a major precast/prestressed manufacturer. Our products are always designed, manufactured and installed for each individual project. However, we sometimes have a few units sent to... Last reply: David Posada, Apr 11, 2011, 12:45 pm |
|
Duct WorkCI-2009 MRc3.1: Materials Reuseposted by Holly Himes on Oct 5, 2011, 6:17 pm
I think I know the answer, but can duct work be counted towards material re-use? I think not as it is MEP material and if being used for the same function it doesn't meet the criteria of being... Last reply: Peter Doo, May 7, 2012, 4:26 pm |
|
Reusing salvaged on-site materialsCI-2009 MRc3.1: Materials Reuseposted by Kathleen Burke on Feb 16, 2012, 8:17 am
can we use the salvaged materials from our site in another project site? For instance this is in a mall and they would uuse the ceiling tile from our project in another place in the mall? Last reply: Kathleen Burke, Feb 16, 2012, 2:02 pm |
|
MR3 or MR1.2?CI-2009 MRc3.1: Materials Reuseposted by Kenny Grossman on Mar 5, 2012, 5:45 pm
I've got a project where nearly nothing has changed between tenants. It seems that the interior materials would qualify for MR1.2 (where it would get two points for being over 60%), but I was... Last reply: Susie Spivey-Tilson, Mar 12, 2012, 12:52 pm |
|
Reclaimed Wood Reused for Restaurant Seating and Wall PanelsCI-2009 MRc3.1: Materials Reuseposted by Abena Darden on Jun 21, 2012, 8:12 pm
We recently received a review back stating that the reclaimed... Last reply: Abena Darden, Jun 21, 2012, 9:52 pm |
|
Material Reused in another locationCI-2009 MRc3.1: Materials Reuseposted by Sustentator Argentina on Oct 31, 2012, 3:09 pm
Hello. I have a question for something that I might be interpreting wrongly because of language. "Materiales Salvaged on site but reused in different-another location (can also count for MR2)"... Last reply: Tristan Roberts, Nov 23, 2012, 10:21 pm |