Must have VAV system for Option 1?CI-2009 EAc1.3: Optimize energy performance - HVACposted by Dave Intner on Feb 8, 2010, 5:30 pm
When we look into the LEED Reference Guide for Option 1, it seems to require a... Last reply: Paul Conrad, Mar 31, 2011, 10:25 am |
|
What if no fan/pump motors are greater than or equal to 5 hp?CI-2009 EAc1.3: Optimize energy performance - HVACposted by Heather Langford on Feb 26, 2010, 9:57 am
Option 1 of this credit states that all motors 5 hp and greater must have VFDs that decrease fan power to 30%. If none of the installed fan motors are 5 hp or greater, can this credit be... Last reply: Sunayana Jain, Jan 28, 2014, 3:05 pm |
|
Applicability of CPG sections 2.9 and 3.10CI-2009 EAc1.3: Optimize energy performance - HVACposted by Clark Denson on Feb 26, 2010, 10:08 am
Like Heather's question above, what if the equipment to be installed is less than 5 hp AND doesn't fall under the HVAC equipment categories listed in section 2.9 of the CPG, such as Variable... Last reply: John Bauer, Jul 30, 2010, 2:53 pm |
|
Base line considerationCI-2009 EAc1.3: Optimize energy performance - HVACposted by Pierre Dammous on Apr 30, 2010, 10:24 am
What should we consider as baseline if we are replacing some of the HVAC equipments? Last reply: Erik Dyrr, May 5, 2010, 6:05 pm |
|
HVAC system ModulationCI-2009 EAc1.3: Optimize energy performance - HVACposted by Pierre Dammous on Apr 30, 2010, 11:37 am
Considering a multi-zoning office with separate constant volume systems and zone control on every solar exposure, private office & special occupancies; can modulation of HVAC system in... Last reply: amy amster, Jul 8, 2010, 9:13 pm |
|
Clean room projectCI-2009 EAc1.3: Optimize energy performance - HVACposted by javier bolanos zeledon on Jul 30, 2010, 12:13 am
How can I model a clean room project where there is a lot of non process load in the HVAC. Can I assume HVAC as process load since it is not just for human comfort and is also for having the... Last reply: Paul Conrad, Jul 30, 2010, 12:28 pm |
|
Non-occupied SpacesCI-2009 EAc1.3: Optimize energy performance - HVACposted by James Del Monaco on Aug 24, 2010, 6:42 pm
I'm working on a TI project where the tenant occupies 2 floors of an 8-story office building. I have an overhead... Last reply: Paul Conrad, Aug 25, 2010, 9:55 am |
|
Water Source Heat PumpsCI-2009 EAc1.3: Optimize energy performance - HVACposted by Jonathon Pfantz on Sep 8, 2010, 11:16 am
I have a small project where the existing system in a 10 story building is a water source heat pump system. From what I gather, this type of system is not very friendly towards achieving LEED CI... Last reply: Paul Conrad, Sep 8, 2010, 11:27 am |
|
ASHRAE Interactive Forms for LEED TemplateCI-2009 EAc1.3: Optimize energy performance - HVACposted by Jonathon Pfantz on Sep 16, 2010, 1:00 pm
Has anybody else had any problems using the ASHRAE 90.1-2007 Interactive Forms required for this credit when pursuing the building simulation option? The lighting form, for example, will not... Last reply: Paul Conrad, Sep 21, 2010, 10:10 am |
|
Part-load condition calculations using HAPCI-2009 EAc1.3: Optimize energy performance - HVACposted by LarsonBinkley Employees on Sep 17, 2010, 3:36 pm
I am working on a small office space. I am trying to get 5 points for equipment efficiency. CPG section 1.4 indicates to provide calculations for part-load condition. It is not clear to me what... Last reply: Rudolph Carneiro, Mar 19, 2013, 4:36 pm |