Walking distance should be measured from a building entrance to the bus stop or rail station. This path must follow sidewalks and other walkable areas. Crossing highways, lawns or other private areas is not considered an acceptable part of pedestrian access.
For WEc1.2: No Potable Water Use or No Irrigation, projects have to achieve a 50% reduction in total water applied in addition to eliminating irrigating with potable water.
Once you have outlined your LEED project boundary, determined your project’s open space zoning requirements, and know whether or not you are achieving SSc2, then you can begin incorporating the required amount of open space into the design.
Will your project earn SSc2: Development Density and Community Connectivity? If so, you can include in your calculations the area of a green roof that contains native or adapted species.
Use LEED point calculators built into online product catalogs such as those powered by ecoScorecard to streamline data collection and generate submittal documents:
A BMS typically includes some M&V capabilities. In buildings with these systems planned or already installed, the cost premium for M&V should be smaller than the percentages given above.
Studies find that, for new construction the combined cost of the installed equipment and the first year of monitoring is less than 1% of the total project cost for buildings larger than 150,000 ft2, and less than 1.5% for smaller buildings.