BOD and OPR

CI-v4 EAp1: Fundamental commissioning and verification
posted by Erin Rowe on Jul 18, 2016, 11:52 pm

Meghan McAvoy Sustainable Programs Manager GHT Limited LEEDuser Premium Member 4 thumbs up July 19, 2016- 8:42 am Hello Erin, First thing's first.. and this probably sounds like a silly question given which part of the forum we're in.. but is this a LEED v4 project? I just want to confirm because the level of detail expected of a v4 project is going to be arguably greater than that of a v3 OPR/BOD. I think you're general assumption about the gist of an OPR is correct, though. I've worked on more than a few LEED projects (NC and CI), and the level of detail I've seen...

Last reply: Meghan McAvoy, Jul 21, 2016, 10:10 am

Untenanted spaces with no lease agreements

CS-2009 IEQp1: Minimum IAQ Performance
posted by John Mader on Jun 29, 2016, 3:53 am

We have a question about retail tenant spaces inside an office building. The owner will provide the retail spaces as cold shells for the retail tenants to fit out after the building is complete....

Last reply: John Mader, Jul 4, 2016, 10:55 pm

Confidential lease agreements cannot be obtained

CS-2009 IEQp1: Minimum IAQ Performance
posted by John Mader on Jun 29, 2016, 3:50 am

Our project is an office building with some retail spaces on its lower floors that have already been leased. We are pursuing LEED CS v2009 and have made the first Design Submission and are now...

Replace All Filtration Media

EBOM-2009 IEQc1.5: IAQ Best Management Practices—Facility Alterations and Additions
posted by Ran Zhang on Jun 14, 2016, 2:36 am

Hi I am working on a project located in Tokyo Japan. We are aiming to pursue IEQ c1.5 and thinking about the requirements regarding the filtration media replacement right now. As replacing all...

Last reply: Trista Little, Jun 14, 2016, 3:02 pm

Chilled Beam System Energy Modeling- CS v2009

CS-2009 EAp2: Minimum Energy Performance
posted by Shenhao Li on May 6, 2016, 5:14 am

Hello Everyone,

I have an office project which is designed to use a little compicated HVAC system. There are 3 Central Heat Recovery Units on the roof top to provide pre-cooled/heated...

Last reply: Shenhao Li, May 10, 2016, 5:55 am

Non-direct Purchase Item

EBOM-2009 MRc1: Sustainable Purchasing—Ongoing Consumables
posted by Ran Zhang on Apr 26, 2016, 2:15 am

The project I am working for does not pay for any toner cartridges as they are included in the maintenance contract. In this case, shall we count it zero or need to get the standard price if they...

CCHP Modeling

NC-2009 EAp2: Minimum Energy Performance
posted by Jie Shen on Apr 22, 2016, 5:04 am

Consultant

ERM

Apr 20 2016

Guest

CCHP System modeling

Project Location: Japan

My project is provided by CCHP system which owned by third party, the CCHP...

Last reply: Marcus Sheffer, Apr 25, 2016, 3:28 pm

CCHP System modeling

NC-2009 EAp2: Minimum Energy Performance
posted by Jie Shen on Apr 20, 2016, 10:07 pm

My project is provided by CCHP system which owned by third party, the CCHP has two gas generators, one heat recovered gas absorption chiller, two normal chillers and two boilers.
1)chilled...

DCV requirement for high-occupancy areas

CS-2009 EAp2: Minimum Energy Performance
posted by Shenhao Li on Apr 4, 2016, 11:50 pm

Hello!
We have a canteen project in Shanghai. The building has three floors, total GFA is 64,067 square feet. The baseline HVAC system type is system 6.
In the second floor, there are...

Last reply: Marcus Sheffer, Apr 5, 2016, 10:48 am

single zone or multi-zone calculation?

NC-2009 IEQp1: Minimum IAQ Performance
posted by Hongyun Zhou on Mar 29, 2016, 2:04 am

I have a project, which have two types of system:
1. OA system offering the fresh air to each room, and each room has an individual fan coil unit .
2. OA system offering the fresh air...

Last reply: Hongyun Zhou, Mar 31, 2016, 9:41 pm