We are wrapping up our second semester and finishing our performance period, we expect soon to have the first building in Mexico certified under a LEED-Lab. We are so happy and we would like to...

Requirements for instant water heater with no storage tank

NC-2009 EAp2: Minimum Energy Performance
posted by Gustavo De las Heras Izquierdo on Jan 27, 2017, 10:04 pm

Hallo,

I have read the insulation requirements in Section 7.4.3 but it seems to focus on circulating and non-circulating systems with a storage tank.

Does anyone know insulation...

Last reply: Marcus Sheffer, Jan 29, 2017, 1:53 pm

Leed Footprint exceeds leed Boundary

NC-2009 SSc5.2: Site development - maximize open space
posted by Jorge López de Obeso on Jun 9, 2016, 12:33 pm

Hi, I'm having some problems with a project.
Turns out that local requirements allow me to expand mi building in my superior floors (By this I mean that above my ground floor I can build...

Last reply: Tristan Roberts, Jan 17, 2017, 5:17 pm

We are in the process of

EBOM-v4 WEp1: Indoor water use reduction
posted by LEED Pro Consultant on Jan 13, 2015, 2:23 pm

We are in the process of certifying a Core and Shell building which does not have a previous LEED certification. There is an inquiry regarding tenant engagement and responsibilities, in order to...

Last reply: Tristan Roberts, Jan 17, 2017, 1:15 pm

LEED O&M on a portion of a building

EBOM-v4 MPR3: Must comply with project size requirements
posted by LEED Pro Consultant on Jan 14, 2015, 7:12 pm

Would a CI project (not LEED) that complies with the MPR's but consists of only a portion of a building (5 levels) be elegible for a LEED O&M certification?

A single entity owns the...

Last reply: Tristan Roberts, Jan 17, 2017, 1:05 pm

10% exemption

EBOM-2009 IEQp1: Minimum IAQ Performance
posted by Gustavo De las Heras Izquierdo on May 17, 2016, 6:41 pm

Is it allowed to exclude up to 10% of spaces from this prerequisite?

Our project is a 20-story building that complies with the ventilation rates but there is an office in the core that...

Last reply: Michael Smithing, Jan 16, 2017, 7:27 pm

BMS

EBOM-2009 EAc2.3: Existing Building Commissioning—Ongoing Commissioning
posted by Gustavo De las Heras Izquierdo on Dec 23, 2016, 12:58 pm

Hallo,

We are working on two projects located in Mexico DF. One of them doesn't have a BMS and the other has a BMS but it does not provide trend graphs. Are these projects eligible for...

Last reply: Scott Bowman, Jan 12, 2017, 6:05 pm

Definition of Landfill

NC-2009 MRc2: Construction Waste Management
posted by Adrian Arenas on Nov 28, 2016, 7:13 pm

you read the posts on this forum regarding mine rehabilitation? Open http://www.leeduser.com/credit/NC-2009/MRc2?all-comments=true in your browser and then search for mine. One in particular to look...

Last reply: Michelle Reott, Dec 27, 2016, 12:23 pm

HVAC Appropriate Zoning and Control

CI-2009 EAc1.3: Optimize energy performance - HVAC
posted by Gabriela Crespo on Aug 5, 2016, 12:35 pm

Dear all,

We are working on a Commercial Interiors project, where there is a...

Last reply: Bazeeth Ahamed K M, Nov 29, 2016, 12:56 am

Appendix G Oversizing

CS-2009 EAc1: Optimize Energy Performance
posted by Jorge Torres-Coto on Sep 19, 2016, 12:45 pm

I have a reviewer requesting that we oversize the PROPOSED case for a "possibly conditioned in the future" warehouse.
We have usually modeled the BASELINE case and PROPOSED case identical,...