LEED O&M on a portion of a building

EBOM-v4 MPR3: Must comply with project size requirements
posted by LEED Pro Consultant on Jan 14, 2015, 7:12 pm

Would a CI project (not LEED) that complies with the MPR's but consists of only a portion of a building (5 levels) be elegible for a LEED O&M certification?

A single entity owns the...

Last reply: Tristan Roberts, Jan 17, 2017, 1:05 pm

10% exemption

EBOM-2009 IEQp1: Minimum IAQ Performance
posted by Gustavo De las Heras Izquierdo on May 17, 2016, 6:41 pm

Is it allowed to exclude up to 10% of spaces from this prerequisite?

Our project is a 20-story building that complies with the ventilation rates but there is an office in the core that...

Last reply: Michael Smithing, Jan 16, 2017, 7:27 pm

BMS

EBOM-2009 EAc2.3: Existing Building Commissioning—Ongoing Commissioning
posted by Gustavo De las Heras Izquierdo on Dec 23, 2016, 12:58 pm

Hallo,

We are working on two projects located in Mexico DF. One of them doesn't have a BMS and the other has a BMS but it does not provide trend graphs. Are these projects eligible for...

Last reply: Scott Bowman, Jan 12, 2017, 6:05 pm

Definition of Landfill

NC-2009 MRc2: Construction Waste Management
posted by Adrian Arenas on Nov 28, 2016, 7:13 pm

you read the posts on this forum regarding mine rehabilitation? Open http://www.leeduser.com/credit/NC-2009/MRc2?all-comments=true in your browser and then search for mine. One in particular to look...

Last reply: Michelle Reott, Dec 27, 2016, 12:23 pm

HVAC Appropriate Zoning and Control

CI-2009 EAc1.3: Optimize energy performance - HVAC
posted by Gabriela Crespo on Aug 5, 2016, 12:35 pm

Dear all,

We are working on a Commercial Interiors project, where there is a...

Last reply: Bazeeth Ahamed K M, Nov 29, 2016, 12:56 am

Appendix G Oversizing

CS-2009 EAc1: Optimize Energy Performance
posted by Jorge Torres-Coto on Sep 19, 2016, 12:45 pm

I have a reviewer requesting that we oversize the PROPOSED case for a "possibly conditioned in the future" warehouse.
We have usually modeled the BASELINE case and PROPOSED case identical,...

Last reply: Marcus Sheffer, Sep 19, 2016, 1:00 pm

Waste Material reused "on-site"

NC-2009 MRc2: Construction Waste Management
posted by Adrian Arenas on Jul 28, 2016, 2:17 pm

Construction Waste Management- Regarding waste material reused on site, our project is currently reusing...

Last reply: Michelle Reott, Aug 19, 2016, 5:00 pm

Tenants

EBOM-2009 IEQc2.3: Occupant Comfort—Thermal Comfort Monitoring
posted by Gustavo De las Heras Izquierdo on Jul 1, 2016, 2:09 pm

Does anyone know if all the tenants need to be included in this credit? We are working on a 70-tenants office building and I guess it will be difficult to coordinate with all of them.

Is...

Last reply: Ben Stanley, Aug 19, 2016, 12:48 pm

Frequency of rides per day that have to be given by the shuttle

NC-2009 SSc4.1: Alternative transportation - public transportation access
posted by Jorge López de Obeso on Aug 9, 2016, 2:02 pm

We are working on a project in which the nearest bus stop is just over a quarter mile so it is proposed to provide a shuttle service to take users to the bus stop. The question is what should be...

Last reply: Marilyn Specht, Aug 14, 2016, 8:30 pm

Urinals on residencial

NC-2009 WEc3: Water Use Reduction
posted by Alejandro Macias on Apr 12, 2016, 2:36 pm

I m working on a dormitory for kids. On the project we have bathrooms that only will be used by the kids (I am considering them as residencial), and other restrooms that will only be used for the...