SS1 Path 11 On-site Renewable Energy

CI-2009 SSc1: Site Selection
posted by Timothy Fry on Nov 4, 2010, 3:54 pm

The building we are outfitting has Solar PV on site, an estimated 17,800kWh annual production. Half of it feeds a DC power Hydrogen electrolyzer that is used within the building and the other...

Last reply: Tristan Roberts, Nov 12, 2010, 10:42 pm

50 % Pervious Pavement or Each Paver need to be 50% Pervious?

CI-2009 SSc1: Site Selection
posted by Simon Sue on Sep 13, 2010, 3:57 am

Hi,

when i look at SSC1 path 4, i keep asking the above question to myself,

therefore, which one is the correct defination for "2. indentify all hardscape surfaces that are open...

Last reply: Tristan Roberts, Sep 28, 2010, 11:26 pm

Default value for open grid paver.

CI-2009 SSc1: Site Selection
posted by Simon Sue on Sep 13, 2010, 3:59 am

Hi all,
i facing some difficulty to look for runoff coefficient value for open grid paver made locally here in Taiwan. Does LEED give any default value for open grid paver?
any advice...

Last reply: Tristan Roberts, Sep 28, 2010, 10:16 pm

SS credit 1: Option 2 path

CI-2009 SSc1: Site Selection
posted by Kevin Gilleran on Sep 8, 2010, 2:29 pm

Hi,
As part off a recent CI design review we have found a building where as part of the enticement for the tenant to move has offered to upgrade portions of the building and in particular...

Last reply: Kevin Gilleran, Sep 8, 2010, 3:47 pm

How exemplary do you have to be for Path 12?

CI-2009 SSc1: Site Selection
posted by Tristan Roberts on Dec 11, 2009, 2:34 pm

The LEED Reference Guide seems to give conflicting advice on how to pursue Path 12 of this credit.

On page 66, the basic description for Path 12 says that "the requirements of another LEED...

Last reply: Anthony Brower, Sep 1, 2010, 6:15 pm

Can we pursue LEED CI?

CI-2009 SSc1: Site Selection
posted by Joel Loes on Jun 17, 2010, 11:34 am

We are a general contractor, and these days we've been doing a lot of tenant improvements around the city.

As a demonstration tool for what we're capable of, we'd like to pursue LEED CI...

Last reply: Erin Cooper, Jul 15, 2010, 2:54 pm

Path 7 and 8: Irrigation

CI-2009 SSc1: Site Selection
posted by Edwin Wealend on Jun 7, 2010, 9:54 pm

Hi,

We are working on a project in China (using CI 2009), its a warehouse converted into an office.

We are trying to gain credits from path 7&8, reduction of irrigation water,...

Last reply: Rick Ferrara, Jun 7, 2010, 11:27 pm

Better option for going into a LEED-CS Gold Certified Building

CI-2009 SSc1: Site Selection
posted by Dean Barone on Dec 6, 2009, 5:47 am

Our client is going into a LEED Certified building and will automatically get 5 points. However, when we will look at Option 2 - we can achieve up to 12 points by meeting several path...